Pay And Download
$15.00
Complete Test Bank With Answers
Sample Questions Posted Below
Chapter 05
Gido & Clements
1. The estimated resources required for an activity will influence the estimated duration to perform the activity.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect The estimated resources required for an activity will influence the estimated duration to
perform the activity.
The estimated resources required for an activity will influence the estimated duration to
perform the activity.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVE
SUPM.GIDO.15.05.01 – 1. Estimate the resources required for activities
S:
NATIONAL STANDARD
United States – BUSPROG: Communications
S:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
2. The estimated activity resources will also be used later for estimating activity costs and determining the project budget.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect The estimated activity resources will also be used later for estimating activity costs and
determining the project budget.
The estimated activity resources will also be used later for estimating activity costs and
determining the project budget.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIV
SUPM.GIDO.15.05.01 – 1. Estimate the resources required for activities
ES:
NATIONAL STANDAR
United States – BUSPROG: Communications
DS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
3. It is a good practice to have the person who will be responsible for performing activities in a project estimate the
duration for other activities to be completed by other resources although the person might not have experience with those
activities.
a. True
b. False
Copyright Cengage Learning. Powered by Cognero. Page 1Chapter 05
Gido & Clements
ANSWER: False
FEEDBACK: Correct Incorrect It is a good practice to have the person who will be responsible for performing a specific activity
estimate the duration for that activity.
It is a good practice to have the person who will be responsible for performing a specific activity
estimate the duration for that activity.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECT
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
IVES:
NATIONAL STANDA
RDS:
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 2/18/2017 2:17 PM
4. For large projects that involve several hundred people performing various activities over several years, it is practical to
have each person estimate activity durations at the beginning of the project.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect For large projects that involve several hundred people performing various activities over several
years, it may not be practical to have each person estimate activity durations at the beginning of the
project.
For large projects that involve several hundred people performing various activities over several
years, it may not be practical to have each person estimate activity durations at the beginning of the
project.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
True / False
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
5. Each organization or subcontractor responsible for a group or type of activities should always designate an
inexperienced individual to estimate the durations for all the activities for which the organization or subcontractor is
Copyright Cengage Learning. Powered by Cognero. Page 2Chapter 05
Gido & Clements
responsible.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect Each organization or subcontractor responsible for a group or type of activities may designate an
experienced individual to estimate the durations for all the activities for which the organization or
subcontractor is responsible.
Each organization or subcontractor responsible for a group or type of activities may designate an
experienced individual to estimate the durations for all the activities for which the organization or
subcontractor is responsible.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
True / False
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
6. The estimated duration for an activity must be based on the estimated quantity of resources required to perform the
activity.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect The estimated duration for an activity must be based on the estimated quantity of resources
required to perform the activity.
The estimated duration for an activity must be based on the estimated quantity of resources
required to perform the activity.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTI
VES:
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
NATIONAL STANDAR
United States – BUSPROG: Communications
DS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
Copyright Cengage Learning. Powered by Cognero. Page 3Chapter 05
Gido & Clements
7. The estimated duration should be aggressive and unrealistic.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect The estimated duration should be aggressive, yet realistic.
The estimated duration should be aggressive, yet realistic.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
NATIONAL STANDARDS: United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 2/18/2017 2:18 PM
8. Playing the game of inflating estimated durations in anticipation of the project manager negotiating shorter durations is
a good practice.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect Playing the game of inflating estimated durations in anticipation of the project manager negotiating
shorter durations is not a good practice.
Playing the game of inflating estimated durations in anticipation of the project manager negotiating
shorter durations is not a good practice.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJEC
TIVES:
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
NATIONAL STAND
ARDS:
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
9. Padding estimates with the vision of becoming a hero when the activities are completed in less time than estimated is
not a good practice.
a. True
b. False
ANSWER: True
Copyright Cengage Learning. Powered by Cognero. Page 4Chapter 05
Gido & Clements
FEEDBACK: Correct Incorrect Padding estimates with the vision of becoming a hero when the activities are completed in less
time than estimated is not a good practice.
Padding estimates with the vision of becoming a hero when the activities are completed in less
time than estimated is not a good practice.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJEC
TIVES:
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
NATIONAL STAND
ARDS:
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
10. At the beginning of every project, it is possible to estimate the durations for all activities with a high level of
confidence regarding their accuracy.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect At the beginning of the project, it may not be possible to estimate the durations for all activities
with a level of confidence regarding their accuracy.
At the beginning of the project, it may not be possible to estimate the durations for all activities
with a level of confidence regarding their accuracy.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJEC
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
TIVES:
NATIONAL STAND
United States – BUSPROG: Communications
ARDS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
11. The project team can progressively elaborate the estimated durations as more information is known or becomes clear
to allow for more accurate estimated durations.
a. True
b. False
ANSWER: True
FEEDBACK: Correct The project team can progressively elaborate the estimated durations as more information is known or
becomes clear to allow for more accurate estimated durations.
Copyright Cengage Learning. Powered by Cognero. Page 5Chapter 05
Gido & Clements
Incorrect The project team can progressively elaborate the estimated durations as more information is known or
becomes clear to allow for more accurate estimated durations.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE
True / False
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
CTIVES:
NATIONAL STAN
United States – BUSPROG: Communications
DARDS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
12. A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a
network diagram.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect A consistent time base, such as hours or days or weeks, should be used for all the estimated
durations of activities in a network diagram.
A consistent time base, such as hours or days or weeks, should be used for all the estimated
durations of activities in a network diagram.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECT
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
IVES:
NATIONAL STANDA
United States – BUSPROG: Communications
RDS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
13. The sponsor or customer often states the project required completion time in the project charter, RFP, or contract.
a. True
b. False
ANSWER: True
FEEDBACK: Correct The sponsor or customer often states the project required completion time in the project
charter, RFP, or contract.
Copyright Cengage Learning. Powered by Cognero. Page 6Chapter 05
Gido & Clements
Incorrect The sponsor or customer often states the project required completion time in the project
charter, RFP, or contract.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIV
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
ES:
NATIONAL STANDAR
United States – BUSPROG: Communications
DS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
14. The contractor may not want to commit to completing the project by a specific date until the customer has approved
the contract.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect The contractor may not want to commit to completing the project by a specific date until the
customer has approved the contract.
The contractor may not want to commit to completing the project by a specific date until the
customer has approved the contract.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTI
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
VES:
NATIONAL STANDA
RDS:
United States – BUSPROG: Ethics
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
15. The latest finish time for a specific activity must be the same as or earlier than the earliest of all the latest start times of
all the activities emerging directly from that specific activity.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect The latest finish time for a specific activity must be the same as or earlier than the earliest of all the
latest start times of all the activities emerging directly from that specific activity.
The latest finish time for a specific activity must be the same as or earlier than the earliest of all the
latest start times of all the activities emerging directly from that specific activity.
POINTS: 1
Copyright Cengage Learning. Powered by Cognero. Page 7Chapter 05
Gido & Clements
DIFFICULTY: Easy
QUESTION TYPE
True / False
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.04 – 4. Determine the latest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
16. If the total slack is zero, the activities on the path do not need to be accelerated but cannot be delayed.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect If the total slack is zero, the activities on the path do not need to be accelerated but cannot be
If the total slack is zero, the activities on the path do not need to be accelerated but cannot be
delayed.
delayed.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES
SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
:
NATIONAL STANDARDS
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
17. A Gantt chart is the often the name for the network diagram tool for looping and laddering.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect A Gantt chart is the often the name for the bar chart tool for planning and scheduling.
A Gantt chart is the often the name for the bar chart tool for planning and scheduling.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
Copyright Cengage Learning. Powered by Cognero. Page 8Chapter 05
Gido & Clements
LEARNING OBJECTIVES: NATIONAL STANDARDS: SUPM.GIDO.15.05.06 – 6. Prepare a project schedule
United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 2/18/2017 2:22 PM
18. This longest path in the overall network diagram is called the network path.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect This longest path in the overall network diagram is called the critical path.
This longest path in the overall network diagram is called the critical path.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: NATIONAL STANDARDS: SUPM.GIDO.15.05.07 – 7. Identify and explain the critical path
United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
19. One way to determine which activities make up the critical path is to find which ones have the least slack.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect One way to determine which activities make up the critical path is to find which ones have
the least slack.
One way to determine which activities make up the critical path is to find which ones have
the least slack.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVE
S:
NATIONAL STANDARD
S:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
SUPM.GIDO.15.05.07 – 7. Identify and explain the critical path
United States – BUSPROG: Communications
20. The project control process starts with establishing a baseline plan that shows how the project scope will be
accomplished beyond the schedule and over budget.
Copyright Cengage Learning. Powered by Cognero. Page 9Chapter 05
Gido & Clements
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect The project control process starts with establishing a baseline plan that shows how the project scope
will be accomplished on schedule and within budget.
The project control process starts with establishing a baseline plan that shows how the project scope
will be accomplished on schedule and within budget.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
NATIONAL STAN
DARDS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED
2/18/2017 2:28 PM
:
SUPM.GIDO.15.05.08 – 8. Discuss the project control process
United States – BUSPROG: Communications
21. Once this baseline plan is agreed upon by the customer and the contractor or project team, the project work can be
performed.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect Once this baseline plan is agreed upon by the customer and the contractor or project team, the
project work can be performed.
Once this baseline plan is agreed upon by the customer and the contractor or project team, the
project work can be performed.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTI
VES:
SUPM.GIDO.15.05.08 – 8. Discuss the project control process
NATIONAL STANDA
RDS:
United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
22. It is necessary to monitor the progress to ensure that everything is going according to the plan.
a. True
b. False
Copyright Cengage Learning. Powered by Cognero. Page 10Chapter 05
Gido & Clements
ANSWER: True
FEEDBACK: Correct Incorrect It is necessary to monitor the progress to ensure that everything is going according to the
plan.
plan.
It is necessary to monitor the progress to ensure that everything is going according to the
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.08 – 8. Discuss the project control process
NATIONAL STANDARDS: United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
23. Project management is a proactive approach to controlling a project to ensure that the project objective is
accomplished, even when things do not go according to plan.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect Project management is a proactive approach to controlling a project to ensure that the project
objective is accomplished, even when things do not go according to plan.
Project management is a proactive approach to controlling a project to ensure that the project
objective is accomplished, even when things do not go according to plan.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
True / False
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.08 – 8. Discuss the project control process
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
24. Throughout a project, changes may occur that have an impact on the schedule.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Copyright Cengage Learning. Powered by Cognero. Throughout a project, changes may occur that have an impact on the schedule.
Page 11Chapter 05
Gido & Clements
Incorrect Throughout a project, changes may occur that have an impact on the schedule.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: NATIONAL STANDARDS: SUPM.GIDO.15.05.09 – 9. Develop updated schedules based on actual progress and changes
United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
25. Changes might be initiated by the customer or the project team, or they might be the result of an unanticipated
occurrence.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect Changes might be initiated by the customer or the project team, or they might be the result of an
unanticipated occurrence.
Changes might be initiated by the customer or the project team, or they might be the result of an
unanticipated occurrence.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTI
VES:
SUPM.GIDO.15.05.09 – 9. Develop updated schedules based on actual progress and changes
NATIONAL STANDAR
United States – BUSPROG: Communications
DS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
26. Changes requested early in the project always have more impact on schedule and budget than if they are requested
later in the project.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect Changes requested early in the project may have less impact on schedule and budget than if they
are requested later in the project.
Changes requested early in the project may have less impact on schedule and budget than if they
are requested later in the project.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
Copyright Cengage Learning. Powered by Cognero. Page 12Chapter 05
Gido & Clements
HAS VARIABLES: False
LEARNING OBJECTI
SUPM.GIDO.15.05.09 – 9. Develop updated schedules based on actual progress and changes
VES:
NATIONAL STANDA
RDS:
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 2/18/2017 2:30 PM
27. When the customer requests a change, the contractor or project team should go ahead with the work without customer
approval of any budget or schedule changes.
a. True
b. False
ANSWER: False
FEEDBACK: Correct Incorrect When the customer requests a change, the contractor or project team should estimate the impact on
the project schedule and budget and then obtain customer approval before proceeding. If the customer
approves the proposed revisions to the project schedule and budget, then any additional activities,
revised estimated durations, and revised estimated resources and associated costs should be
incorporated into the project schedule and budget.
When the customer requests a change, the contractor or project team should estimate the impact on
the project schedule and budget and then obtain customer approval before proceeding. If the customer
approves the proposed revisions to the project schedule and budget, then any additional activities,
revised estimated durations, and revised estimated resources and associated costs should be
incorporated into the project schedule and budget.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE
True / False
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.09 – 9. Develop updated schedules based on actual progress and changes
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
2/18/2017 2:31 PM
28. An updated project schedule can be generated regularly that forecasts whether the project will finish ahead of or
behind its required completion time.
a. True
b. False
ANSWER: True
FEEDBACK: Correct An updated project schedule can be generated regularly that forecasts whether the project will finish
ahead of or behind its required completion time.
Copyright Cengage Learning. Powered by Cognero. Page 13Chapter 05
Gido & Clements
Incorrect An updated project schedule can be generated regularly that forecasts whether the project will finish
ahead of or behind its required completion time.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJEC
SUPM.GIDO.15.05.10 – 10. Discuss and apply approaches to control the project schedule
TIVES:
NATIONAL STAND
United States – BUSPROG: Communications
ARDS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
29. The amount of slack should determine the priority with which these concentrated efforts are applied.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect The amount of slack should determine the priority with which these concentrated efforts are
applied.
The amount of slack should determine the priority with which these concentrated efforts are
applied.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES
SUPM.GIDO.15.05.10 – 10. Discuss and apply approaches to control the project schedule
:
NATIONAL STANDARDS: United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
30. A change in the estimated duration of any activity on that path will cause a corresponding change in the slack for that
path.
a. True
b. False
ANSWER: True
FEEDBACK: Correct Incorrect A change in the estimated duration of any activity on that path will cause a corresponding
change in the slack for that path.
A change in the estimated duration of any activity on that path will cause a corresponding
change in the slack for that path.
POINTS: 1
Copyright Cengage Learning. Powered by Cognero. Page 14Chapter 05
Gido & Clements
DIFFICULTY: Moderate
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTI
VES:
NATIONAL STANDAR
DS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
SUPM.GIDO.15.05.10 – 10. Discuss and apply approaches to control the project schedule
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
31. When estimating resources for activities to estimate the activity’s duration, the
a. b. availability of each resource has to be taken into account.
name of each resource has to be taken into account.
c. cost of each resource has to be taken into account.
d. security clearance of each resource has to be taken into account.
ANSWER: a
FEEDBACK: a. When estimating resources for activities, the availability of each resource has to be
taken into account.
b. When estimating resources for activities, the availability of each resource has to be
taken into account.
c. When estimating resources for activities, the availability of each resource has to be
taken into account.
d. When estimating resources for activities, the availability of each resource has to be
taken into account.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIV
ES:
SUPM.GIDO.15.05.01 – 1. Estimate the resources required for activities
NATIONAL STANDAR
United States – BUSPROG: Communications
DS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
32. It is important to know what types of resources are available, in what quantities, and during what time periods to
determine
a. that the project team will be larger than necessary to complete the project.
b. how to enter resources into a project management information system.
c. if the right types of resources will be available in sufficient quantities during the time periods that the project
requires.
d. that the project will be less expensive than estimated.
Copyright Cengage Learning. Powered by Cognero. Page 15Chapter 05
Gido & Clements
ANSWER: c
FEEDBACK: a. It is important to know what types of resources are available, in what quantities, and
during what time periods to determine if the right types of resources will be available in
sufficient quantities during the time periods that the project requires.
b. It is important to know what types of resources are available, in what quantities, and
during what time periods to determine if the right types of resources will be available in
sufficient quantities during the time periods that the project requires.
c. It is important to know what types of resources are available, in what quantities, and
during what time periods to determine if the right types of resources will be available in
sufficient quantities during the time periods that the project requires.
d. It is important to know what types of resources are available, in what quantities, and
during what time periods to determine if the right types of resources will be available in
sufficient quantities during the time periods that the project requires.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.01 – 1. Estimate the resources required for activities
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
33. When considering the availability of resources, it may be necessary to make some assumptions, such as
a. the unemployment rate in the community.
b. the ability to hire additional individuals with the appropriate expertise in time for when they will be required
to work on a project.
c. the number of project deliverables.
d. the type of organizational structure of the sponsor.
ANSWER: b
Copyright Cengage Learning. Powered by Cognero. Page 16Chapter 05
Gido & Clements
FEEDBACK: a. When considering the availability of resources, it may be necessary to make some
assumptions, such as the ability to hire additional individuals with the appropriate
expertise in time for when they will be required to work on a project.
b. When considering the availability of resources, it may be necessary to make some
assumptions, such as the ability to hire additional individuals with the appropriate
expertise in time for when they will be required to work on a project.
c. When considering the availability of resources, it may be necessary to make some
assumptions, such as the ability to hire additional individuals with the appropriate
expertise in time for when they will be required to work on a project.
d. When considering the availability of resources, it may be necessary to make some
assumptions, such as the ability to hire additional individuals with the appropriate
expertise in time for when they will be required to work on a project.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.01 – 1. Estimate the resources required for activities
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
34. In many cases, especially for smaller projects, most activities involve people resources—that is,
a. all the people who are employed by the project sponsor.
b. all the people who are employed by the project contractor.
c. the members of the project team who may be utilized full time or part time during the project.
d. the stakeholders for the project.
ANSWER: c
FEEDBACK: a. In many cases, especially for smaller projects, most activities involve people resources—
that is, the members of the project team who may be utilized full time or part time during
the project.
b. In many cases, especially for smaller projects, most activities involve people resources—
that is, the members of the project team who may be utilized full time or part time during
the project.
c. In many cases, especially for smaller projects, most activities involve people resources—
that is, the members of the project team who may be utilized full time or part time during
the project.
d. In many cases, especially for smaller projects, most activities involve people resources—
that is, the members of the project team who may be utilized full time or part time during
the project.
Copyright Cengage Learning. Powered by Cognero. Page 17Chapter 05
Gido & Clements
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.01 – 1. Estimate the resources required for activities
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
4/5/2016 10:13 AM
D:
35. The estimated types and quantities of resources required for an activity together with the availability of those
resources will influence the
a. estimated duration for how long it will take to perform the activity.
b. project scope document description.
c. project’s acceptance criteria.
d. actual costs of work performed.
ANSWER: a
FEEDBACK: a. The estimated types and quantities of resources required for an activity together with the
availability of those resources will influence the estimated duration for how long it will
take to perform the activity.
b. The estimated types and quantities of resources required for an activity together with the
availability of those resources will influence the estimated duration for how long it will
take to perform the activity.
c. The estimated types and quantities of resources required for an activity together with the
availability of those resources will influence the estimated duration for how long it will
take to perform the activity.
d. The estimated types and quantities of resources required for an activity together with the
availability of those resources will influence the estimated duration for how long it will
take to perform the activity.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.01 – 1. Estimate the resources required for activities
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
Copyright Cengage Learning. Powered by Cognero. Page 18Chapter 05
Gido & Clements
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
36. When estimating the types and quantities of resources required for each specific activity, it is valuable to involve a
person who
a. is hired by the customer to be a consultant regardless of experience on the type of project.
b. has expertise or experience with the activity to help make the estimate.
c. has experience negotiating contracts.
d. has the most experience using a project management information system.
ANSWER: b
FEEDBACK: a. When estimating the types and quantities of resources required for each specific activity, it
is valuable to involve a person who has expertise or experience with the activity to help
make the estimate.
b. When estimating the types and quantities of resources required for each specific activity, it
is valuable to involve a person who has expertise or experience with the activity to help
make the estimate.
c. When estimating the types and quantities of resources required for each specific activity, it
is valuable to involve a person who has expertise or experience with the activity to help
make the estimate.
d. When estimating the types and quantities of resources required for each specific activity, it
is valuable to involve a person who has expertise or experience with the activity to help
make the estimate.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.01 – 1. Estimate the resources required for activities
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
37. The estimated duration for each activity must be the total elapsed time,
a. the time for the work to be done plus any associated waiting time.
b. the time for the task plus the planning time for the project.
c. the time required for the work times the number of resources assigned to the project.
d. the time for the task plus the time to review and accept the deliverable.
ANSWER: a
Copyright Cengage Learning. Powered by Cognero. Page 19Chapter 05
Gido & Clements
FEEDBACK: a. The estimated duration for each activity must be the total elapsed time, the time for the
work to be done plus any associated waiting time.
b. The estimated duration for each activity must be the total elapsed time, the time for the
work to be done plus any associated waiting time.
c. The estimated duration for each activity must be the total elapsed time, the time for the
work to be done plus any associated waiting time.
d. The estimated duration for each activity must be the total elapsed time, the time for the
work to be done plus any associated waiting time.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
NATIONAL STAN
DARDS:
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED
4/5/2016 10:13 AM
:
38. Having the person who will be responsible for performing a specific activity estimate the duration for that activity
____ from that person and ____ that may be introduced by having one person estimate the durations for all of the
activities.
a. takes more effort, creates a problem
b. gives the status of the project, sets best practices
c. generates a commitment , avoids any bias
d. elevates the placement perception, creates errors
ANSWER: c
FEEDBACK: a. Having the person who will be responsible for performing a specific activity estimate the
duration for that activity generates a commitment from that person and avoids any bias that
may be introduced by having one person estimate the durations for all of the activities.
b. Having the person who will be responsible for performing a specific activity estimate the
duration for that activity generates a commitment from that person and avoids any bias that
may be introduced by having one person estimate the durations for all of the activities.
c. Having the person who will be responsible for performing a specific activity estimate the
duration for that activity generates a commitment from that person and avoids any bias that
may be introduced by having one person estimate the durations for all of the activities.
d. Having the person who will be responsible for performing a specific activity estimate the
duration for that activity generates a commitment from that person and avoids any bias that
may be introduced by having one person estimate the durations for all of the activities.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
Copyright Cengage Learning. Powered by Cognero. Page 20Chapter 05
Gido & Clements
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
39. If an organization or subcontractor has performed similar projects in the past and has kept records of how long specific
activities actually took, these historical data
a. can be used as a guide in estimating the durations of similar activities for future projects.
b. have no value for the current project.
c. should be stored in files.
d. should be shared with the customer after the contract is signed to show that the contractor can complete the
project.
ANSWER: a
FEEDBACK: a. If an organization or subcontractor has performed similar projects in the past and has kept
records of how long specific activities actually took, these historical data can be used as a
guide in estimating the durations of similar activities for future projects.
b. If an organization or subcontractor has performed similar projects in the past and has kept
records of how long specific activities actually took, these historical data can be used as a
guide in estimating the durations of similar activities for future projects.
c. If an organization or subcontractor has performed similar projects in the past and has kept
records of how long specific activities actually took, these historical data can be used as a
guide in estimating the durations of similar activities for future projects.
d. If an organization or subcontractor has performed similar projects in the past and has kept
records of how long specific activities actually took, these historical data can be used as a
guide in estimating the durations of similar activities for future projects.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE 4/5/2016 10:13 AM
Copyright Cengage Learning. Powered by Cognero. Page 21Chapter 05
Gido & Clements
D:
40. People sometimes perform to expectations, their effort will expand to fill the whole number of scheduled days allotted,
a. even if the number of resources assigned to the task is reduced.
b. even if the activity could have been performed in a shorter time.
c. even if part of the time for the task is waiting time.
d. even if the activity could have been performed in a longer time.
ANSWER: b
FEEDBACK: a. People sometimes perform to expectations, their effort will expand to fill the whole
number of scheduled days allotted, even if the activity could have been performed in a
shorter time.
b. People sometimes perform to expectations, their effort will expand to fill the whole
number of scheduled days allotted, even if the activity could have been performed in a
shorter time.
c. People sometimes perform to expectations, their effort will expand to fill the whole
number of scheduled days allotted, even if the activity could have been performed in a
shorter time.
d. People sometimes perform to expectations, their effort will expand to fill the whole
number of scheduled days allotted, even if the activity could have been performed in a
shorter time.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
41. Throughout the performance of the project, some activities will take longer than their estimated duration, others will
be done in less time than their estimated duration, and
a. many will take no time to complete.
b. many will not be completed.
c. others are to be done by two project teams.
d. a few may conform to the estimated duration exactly.
ANSWER: d
Copyright Cengage Learning. Powered by Cognero. Page 22Chapter 05
Gido & Clements
FEEDBACK: a. Throughout the performance of the project, some activities will take longer than their
estimated duration, others will be done in less time than their estimated duration, and a few
may conform to the estimated duration exactly.
b. Throughout the performance of the project, some activities will take longer than their
estimated duration, others will be done in less time than their estimated duration, and a few
may conform to the estimated duration exactly.
c. Throughout the performance of the project, some activities will take longer than their
estimated duration, others will be done in less time than their estimated duration, and a few
may conform to the estimated duration exactly.
d. Throughout the performance of the project, some activities will take longer than their
estimated duration, others will be done in less time than their estimated duration, and a few
may conform to the estimated duration exactly.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
4/5/2016 10:13 AM
D:
42. With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible
to use three time estimates:
a. an original estimate, a petrified estimate, and a most likely estimate.
b. an optimistic estimate, a pessimistic estimate, and a most likely estimate.
c. an optimized estimate, a primary estimate, and a most likely estimate.
d. an opportunity estimate, a pragmatic estimate, and a most likely estimate.
ANSWER: b
Copyright Cengage Learning. Powered by Cognero. Page 23Chapter 05
Gido & Clements
FEEDBACK: a. With projects for which there is a high degree of uncertainty about the estimated durations
for activities, it is possible to use three time estimates: an optimistic estimate, a pessimistic
estimate, and a most likely estimate.
b. With projects for which there is a high degree of uncertainty about the estimated durations
for activities, it is possible to use three time estimates: an optimistic estimate, a pessimistic
estimate, and a most likely estimate.
c. With projects for which there is a high degree of uncertainty about the estimated durations
for activities, it is possible to use three time estimates: an optimistic estimate, a pessimistic
estimate, and a most likely estimate.
d. With projects for which there is a high degree of uncertainty about the estimated durations
for activities, it is possible to use three time estimates: an optimistic estimate, a pessimistic
estimate, and a most likely estimate.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.02 – 2. Estimate the duration for an activity
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
43. In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is
necessary to
a. say who has responsibility for the first task.
b. enter the tasks into a project management information system.
c. select an estimated start time and a required completion time for the overall project.
d. edit the calendars for the resources in the project management information system.
ANSWER: c
Copyright Cengage Learning. Powered by Cognero. Page 24Chapter 05
Gido & Clements
FEEDBACK: a. In order to establish a basis from which to calculate a schedule using the estimated
durations for the activities, it is necessary to select an estimated start time and a required
completion time for the overall project.
b. In order to establish a basis from which to calculate a schedule using the estimated
durations for the activities, it is necessary to select an estimated start time and a required
completion time for the overall project.
c. In order to establish a basis from which to calculate a schedule using the estimated
durations for the activities, it is necessary to select an estimated start time and a required
completion time for the overall project.
d. In order to establish a basis from which to calculate a schedule using the estimated
durations for the activities, it is necessary to select an estimated start time and a required
completion time for the overall project.
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPROG: Communications
DARDS:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
44. Earliest start time (ES) is the earliest time at which a specific activity can begin
a. calculated on the basis of the project estimated start time and the estimated durations of preceding activities.
b. calculated on the basis of the project estimated finish time and the estimated durations of preceding activities.
c. calculated on the basis of the project estimated start time and the estimated durations of succeeding activities.
d. calculated on the basis of the project estimated start time and the estimated durations of approaching
activities.
ANSWER: a
Copyright Cengage Learning. Powered by Cognero. Page 25Chapter 05
Gido & Clements
FEEDBACK: a. Earliest start time (ES) is the earliest time at which a specific activity can begin, calculated
on the basis of the project estimated start time and the estimated durations of preceding
activities.
b. Earliest start time (ES) is the earliest time at which a specific activity can begin, calculated
on the basis of the project estimated start time and the estimated durations of preceding
activities.
c. Earliest start time (ES) is the earliest time at which a specific activity can begin, calculated
on the basis of the project estimated start time and the estimated durations of preceding
activities.
d. Earliest start time (ES) is the earliest time at which a specific activity can begin, calculated
on the basis of the project estimated start time and the estimated durations of preceding
activities.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
45. Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated
a. by subtracting the activity’s estimated duration from the earliest finish time of the activity’s predecessor: EF =
EF predecessor – Estimated Duration.
b. by subtracting the activity’s estimated duration to the activity’s earliest start time: EF = ES – Estimated
Duration.
c. by adding the activity’s estimated duration to the earliest start time of the activity’s succeeding activity: EF =
ES succeeding activity + Estimated Duration.
d. by adding the activity’s estimated duration to the activity’s earliest start time: EF = ES + Estimated Duration.
ANSWER: d
FEEDBACK: a. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
b. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
c. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
Copyright Cengage Learning. Powered by Cognero. Page 26Chapter 05
Gido & Clements
d. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
46. The ES and EF times are determined by calculating forward, that is, by
a. adding all the times together for the project.
b. working through the network diagram from the beginning of the project to the end of the project.
c. calculating the optimistic and pessimistic times for the project.
d. working through the network diagram from the end of the project to the beginning of the project.
ANSWER: b
FEEDBACK: a. The ES and EF times are determined by calculating forward, that is, by working through
the network diagram from the beginning of the project to the end of the project.
b. The ES and EF times are determined by calculating forward, that is, by working through
the network diagram from the beginning of the project to the end of the project.
c. The ES and EF times are determined by calculating forward, that is, by working through
the network diagram from the beginning of the project to the end of the project.
d. The ES and EF times are determined by calculating forward, that is, by working through
the network diagram from the beginning of the project to the end of the project.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
Copyright Cengage Learning. Powered by Cognero. Page 27Chapter 05
Gido & Clements
DATE MODIFIE
D:
4/5/2016 10:13 AM
47. The earliest start time for a specific activity must be ____ the latest of all the earliest finish times of all the activities
leading directly into that specific activity.
a. earlier than
b. the same as
c. the same as or later than
d. later than
ANSWER: c
FEEDBACK: a. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
b. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
c. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
d. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
48. Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2
days.
a. day 5
b. day 3
c. day 1
d. ANSWER: a
FEEDBACK: Cannot be calculated based upon information given.
a. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
Copyright Cengage Learning. Powered by Cognero. Page 28Chapter 05
Gido & Clements
b. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
c. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
d. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
49. Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
a. day 5
b. day 3
c. day 1
d. ANSWER: b
FEEDBACK: Cannot be calculated based upon information given.
a. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
b. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
c. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
d. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
Copyright Cengage Learning. Powered by Cognero. Page 29Chapter 05
Gido & Clements
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
50. Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task
C, finishes on day 4, and the duration of Task D is 2 days.
a. day 6
b. day 3
c. day 4
d. Cannot be calculated based upon information given.
ANSWER: c
FEEDBACK: a. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
b. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
c. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
d. The earliest start time for a specific activity must be the same as or later than the latest of
all the earliest finish times of all the activities leading directly into that specific activity.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
51. Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task
C, finishes on day 4, and the duration of Task D is 2 days.
a. day 6
b. day 3
c. day 4
Copyright Cengage Learning. Powered by Cognero. Page 30Chapter 05
Gido & Clements
d. ANSWER: a
FEEDBACK: Cannot be calculated based upon information given.
a. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
b. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
c. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
d. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,
calculated by adding the activity’s estimated duration to the activity’s earliest start time:
EF = ES + Estimated Duration.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.03 – 3. Determine the earliest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
52. Latest finish time (LF) is the latest time by which a specific activity must be
a. started in order for the entire project to be finished by its required completion time.
b. completed in order for the entire project to be finished by its required completion time.
c. started in order for the entire project to be started by its required completion time.
d. completed in order for the entire project to be started by its required completion time.
ANSWER: b
FEEDBACK: a. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
b. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
c. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
d. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
POINTS: 1
Copyright Cengage Learning. Powered by Cognero. Page 31Chapter 05
Gido & Clements
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.04 – 4. Determine the latest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
53. Latest start time (LS) is the latest time by which a specific activity must be
a. started in order for the entire project to be finished by its required completion time.
b. started in order for the entire project to be started by its required completion time.
c. finished in order for the entire project to be finished by its required completion time.
d. finished in order for the entire project to be started by its required completion time.
ANSWER: a
FEEDBACK: a. Latest start time (LS) is the latest time by which a specific activity must be started in order
for the entire project to be finished by its required completion time.
b. Latest start time (LS) is the latest time by which a specific activity must be started in order
for the entire project to be finished by its required completion time.
c. Latest start time (LS) is the latest time by which a specific activity must be started in order
for the entire project to be finished by its required completion time.
d. Latest start time (LS) is the latest time by which a specific activity must be started in order
for the entire project to be finished by its required completion time.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.04 – 4. Determine the latest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
54. Latest start time is calculated by
Copyright Cengage Learning. Powered by Cognero. Page 32Chapter 05
Gido & Clements
a. subtracting the activity’s estimated duration from the activity’s succeeding activity’s latest finish time: LS =
LF succeeding activity – Estimated Duration.
b. adding the activity’s estimated duration to the predecessor of the activity’s latest start time: LS = LS
predecessor + Estimated Duration.
c. subtracting the activity’s estimated duration from the activity’s latest finish time: LS = LF – Estimated
Duration.
d. adding the activity’s estimated duration to the activity’s latest finish time: LS = LF + Estimated Duration.
ANSWER: c
FEEDBACK: a. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
b. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
c. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
d. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
SUPM.GIDO.15.05.04 – 4. Determine the latest start and finish times for activities
NATIONAL STAN
DARDS:
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
55. Calculate the latest finish for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has
a latest start of day 7, and the duration of Task B is 2 days.
a. day 5
b. day 3
c. day 7
d. Cannot be calculated based upon information given.
ANSWER: c
Copyright Cengage Learning. Powered by Cognero. Page 33Chapter 05
Gido & Clements
FEEDBACK: a. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
b. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
c. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
d. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.04 – 4. Determine the latest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
56. Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a
latest start of day 7, and the duration of Task B is 2 days.
a. day 5
b. day 3
c. day 7
d. Cannot be calculated based upon information given.
ANSWER: a
FEEDBACK: a. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
b. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
c. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
d. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
Copyright Cengage Learning. Powered by Cognero. Page 34Chapter 05
Gido & Clements
LEARNING OBJE
CTIVES:
SUPM.GIDO.15.05.04 – 4. Determine the latest start and finish times for activities
NATIONAL STAN
DARDS:
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
57. Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task
E, has a latest start on day 10, and the duration of Task D is 2 days.
a. day 8
b. day 7
c. day 12
d. Cannot be calculated based upon information given.
ANSWER: b
FEEDBACK: a. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
b. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
c. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
d. Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS = LF – Estimated Duration.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
SUPM.GIDO.15.05.04 – 4. Determine the latest start and finish times for activities
NATIONAL STAN
DARDS:
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
58. Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor,
Task E, has a latest start on day 10, and the duration of Task D is 2 days.
a. day 9
b. day 10
c. day 12
Copyright Cengage Learning. Powered by Cognero. Page 35Chapter 05
Gido & Clements
d. ANSWER: a
FEEDBACK: Cannot be calculated based upon information given.
a. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
b. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
c. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
d. Latest finish time (LF) is the latest time by which a specific activity must be completed in
order for the entire project to be finished by its required completion time.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.04 – 4. Determine the latest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
59. Total slack for the project is the difference between
a. LF time of last activity and the project required completion time.
b. EF time of last activity and the project required completion time.
c. ES time of last activity and the project required completion time.
d. LS time of last activity and the project required completion time.
ANSWER: b
FEEDBACK: a. Total slack for the project is the difference between EF time of last activity and the
project required completion time.
b. Total slack for the project is the difference between EF time of last activity and the
project required completion time.
c. Total slack for the project is the difference between EF time of last activity and the
project required completion time.
d. Total slack for the project is the difference between EF time of last activity and the
project required completion time.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
Copyright Cengage Learning. Powered by Cognero. Page 36Chapter 05
Gido & Clements
LEARNING OBJECTI
SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
VES:
NATIONAL STANDA
RDS:
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
60. Total Slack is sometimes called
a. drift.
b. ride.
c. float.
d. sink.
ANSWER: c
FEEDBACK: a. Total Slack is sometimes called float.
b. c. d. Total Slack is sometimes called float.
Total Slack is sometimes called float.
Total Slack is sometimes called float.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
NATIONAL STANDARDS: United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
61. Total slack is calculated for each of the activities by finding the difference between
a. the ES of the activity and the LF of the activity or the difference between the EF and LS of the activity.
b. the EF of the activity and the LS of the activity or the difference between the ES and LF of the activity.
c. the EF of the activity and the LF of the activity or the difference between the ES and LS of the activity.
d. the ES of the activity and the LF of the activity or the difference between the ES and LF of the activity.
ANSWER: c
Copyright Cengage Learning. Powered by Cognero. Page 37Chapter 05
Gido & Clements
FEEDBACK: a. Total slack is calculated for each of the activities by finding the difference between the EF
of the activity and the LF of the activity or the difference between the ES and LS of the
activity.
b. Total slack is calculated for each of the activities by finding the difference between the EF
of the activity and the LF of the activity or the difference between the ES and LS of the
activity.
c. Total slack is calculated for each of the activities by finding the difference between the EF
of the activity and the LF of the activity or the difference between the ES and LS of the
activity.
d. Total slack is calculated for each of the activities by finding the difference between the EF
of the activity and the LF of the activity or the difference between the ES and LS of the
activity.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
62. Negative slack indicates a lack of slack over the entire project and the amount of time
a. an activity must be accelerated to complete the project by the required completion time.
b. an activity must be delayed to complete the project by the required completion time.
c. each activity on the critical must be accelerated to complete the project by the required completion time.
d. all activities in the project must be accelerated to complete the project by the required completion time.
ANSWER: a
FEEDBACK: a. Negative slack indicates a lack of slack over the entire project and the amount of time an
activity must be accelerated to complete the project by the required completion time.
b. Negative slack indicates a lack of slack over the entire project and the amount of time an
activity must be accelerated to complete the project by the required completion time.
c. Negative slack indicates a lack of slack over the entire project and the amount of time an
activity must be accelerated to complete the project by the required completion time.
d. Negative slack indicates a lack of slack over the entire project and the amount of time an
activity must be accelerated to complete the project by the required completion time.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
Copyright Cengage Learning. Powered by Cognero. Page 38Chapter 05
Gido & Clements
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
63. Positive slack indicates the maximum amount of time
a. that the activities on the critical path should be accelerated to complete the project by the required completion
time.
b. that each of the activities in the project can be delayed without jeopardizing completion of the project by the
required completion time.
c. that the activities with the positive slack should be accelerated to complete the project by the required
completion time.
d. that the activities on a particular path can be delayed without jeopardizing completion of the project by the
required completion time.
ANSWER: d
FEEDBACK: a. Positive slack indicates the maximum amount of time that the activities on a particular path
can be delayed without jeopardizing completion of the project by the required completion
time.
b. Positive slack indicates the maximum amount of time that the activities on a particular path
can be delayed without jeopardizing completion of the project by the required completion
time.
c. Positive slack indicates the maximum amount of time that the activities on a particular path
can be delayed without jeopardizing completion of the project by the required completion
time.
d. Positive slack indicates the maximum amount of time that the activities on a particular path
can be delayed without jeopardizing completion of the project by the required completion
time.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
Copyright Cengage Learning. Powered by Cognero. Page 39Chapter 05
Gido & Clements
DATE MODIFIE
D:
4/5/2016 10:13 AM
64. Free slack is the amount of time a specific activity can be
a. postponed without delaying the earliest start time of its immediately preceding activities.
b. postponed without delaying the earliest start time of its immediately succeeding activities.
c. accelerated without delaying the latest start time of its immediately succeeding activities.
d. accelerated without delaying the latest finish time of its immediately preceding activities.
ANSWER: b
FEEDBACK: a. Free slack is the amount of time a specific activity can be postponed without delaying the
earliest start time of its immediately succeeding activities.
b. Free slack is the amount of time a specific activity can be postponed without delaying the
earliest start time of its immediately succeeding activities.
c. Free slack is the amount of time a specific activity can be postponed without delaying the
earliest start time of its immediately succeeding activities.
d. Free slack is the amount of time a specific activity can be postponed without delaying the
earliest start time of its immediately succeeding activities.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
65. Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific
activity and then
a. adding it from the values of total slack for the other activities also entering into that same activity.
b. subtracting it from the values of total slack for the other activities succeeding after that same activity.
c. subtracting it from the values of total slack for the other activities also entering into that same activity.
d. adding it from the values of total slack for the other activities succeeding after that same activity.
ANSWER: c
Copyright Cengage Learning. Powered by Cognero. Page 40Chapter 05
Gido & Clements
FEEDBACK: a. Free slack is calculated by finding the lowest of the values of total slack for all the
activities entering into a specific activity and then subtracting it from the values of total
slack for the other activities also entering into that same activity.
b. Free slack is calculated by finding the lowest of the values of total slack for all the
activities entering into a specific activity and then subtracting it from the values of total
slack for the other activities also entering into that same activity.
c. Free slack is calculated by finding the lowest of the values of total slack for all the
activities entering into a specific activity and then subtracting it from the values of total
slack for the other activities also entering into that same activity.
d. Free slack is calculated by finding the lowest of the values of total slack for all the
activities entering into a specific activity and then subtracting it from the values of total
slack for the other activities also entering into that same activity.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
66. The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task
C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have?
a. Negative 5 days slack.
b. Positive 5 days slack.
c. Positive 17 days slack.
d. Positive 3 days slack.
ANSWER: b
FEEDBACK: a. The total completion time is 25 days. The tasks are planned to take 20 days (7+5+8).
The project has 5 days of slack.
b. The total completion time is 25 days. The tasks are planned to take 20 days (7+5+8).
The project has 5 days of slack.
c. The total completion time is 25 days. The tasks are planned to take 20 days (7+5+8).
The project has 5 days of slack.
d. The total completion time is 25 days. The tasks are planned to take 20 days (7+5+8).
The project has 5 days of slack.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: Multiple Choice
Copyright Cengage Learning. Powered by Cognero. Page 41Chapter 05
Gido & Clements
HAS VARIABLES: False
LEARNING OBJECTI
SUPM.GIDO.15.05.05 – 5. Explain and determine total slack
VES:
NATIONAL STANDA
RDS:
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
67. The estimated duration for each activity is indicated by a bar spanning the period
a. during which the activity is expected to be accomplished.
b. of the part of the activity that has more than one work resource assigned.
c. during which the activity has waiting time for the activity to be accomplished.
d. during which the project is expected to be accomplished.
ANSWER: a
FEEDBACK: a. The estimated duration for each activity is indicated by a bar spanning the period during
which the activity is expected to be accomplished.
b. The estimated duration for each activity is indicated by a bar spanning the period during
which the activity is expected to be accomplished.
c. The estimated duration for each activity is indicated by a bar spanning the period during
which the activity is expected to be accomplished.
d. The estimated duration for each activity is indicated by a bar spanning the period during
which the activity is expected to be accomplished.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
NATIONAL STAN
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED
4/5/2016 10:13 AM
:
SUPM.GIDO.15.05.06 – 6. Prepare a project schedule
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
68. As the project progresses, the actual finish times (AFs) of completed activities will determine
a. the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the
total slack.
b. the earliest start and earliest finish times for the completed activities in the network diagram, as well as the
total slack.
c. the latest start and latest finish times for the remaining activities in the network diagram, as well as the total
slack.
Copyright Cengage Learning. Powered by Cognero. Page 42Chapter 05
Gido & Clements
d. the latest start and latest finish times for the completed activities in the network diagram, as well as the total
slack.
ANSWER: a
FEEDBACK: a. As the project progresses, the actual finish times (AFs) of completed activities will
determine the earliest start and earliest finish times for the remaining activities in the
network diagram, as well as the total slack.
b. As the project progresses, the actual finish times (AFs) of completed activities will
determine the earliest start and earliest finish times for the remaining activities in the
network diagram, as well as the total slack.
c. As the project progresses, the actual finish times (AFs) of completed activities will
determine the earliest start and earliest finish times for the remaining activities in the
network diagram, as well as the total slack.
d. As the project progresses, the actual finish times (AFs) of completed activities will
determine the earliest start and earliest finish times for the remaining activities in the
network diagram, as well as the total slack.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.06 – 6. Prepare a project schedule
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
69. The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task
C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of
seven days. How much slack does the project have now that Task A is finished?
a. Negative 5 days slack.
b. Positive 5 days slack.
c. Positive 16 days slack.
d. Positive 3 days slack.
ANSWER: d
Copyright Cengage Learning. Powered by Cognero. Page 43Chapter 05
Gido & Clements
FEEDBACK: a. The total completion time is 25 days. The tasks were planned to take 20 days (7+5+8).
Task A’s actual finish time is 9 days. The expected time of the project is now 22 days
(9+5+8). The project has 3 days of slack.
b. The total completion time is 25 days. The tasks were planned to take 20 days (7+5+8).
Task A’s actual finish time is 9 days. The expected time of the project is now 22 days
(9+5+8). The project has 3 days of slack.
c. The total completion time is 25 days. The tasks were planned to take 20 days (7+5+8).
Task A’s actual finish time is 9 days. The expected time of the project is now 22 days
(9+5+8). The project has 3 days of slack.
d. The total completion time is 25 days. The tasks were planned to take 20 days (7+5+8).
Task A’s actual finish time is 9 days. The expected time of the project is now 22 days
(9+5+8). The project has 3 days of slack.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.06 – 6. Prepare a project schedule
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
70. The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task
C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of
seven days. What are the ES and EF times for Task B now that Task A is complete?
a. ES = 9, EF = 14
b. ES = 7, EF = 12
c. ES = 5, EF = 14
d. ES = 5, EF = 12
ANSWER: a
FEEDBACK: a. The finish time for Task A is nine days. The ES for Task B is the same as the finish time
for Task A. The EF for Task B is the ES of Task B + Estimated Duration of Task B = 9+5
= 14 days.
b. The finish time for Task A is nine days. The ES for Task B is the same as the finish time
for Task A. The EF for Task B is the ES of Task B + Estimated Duration of Task B = 9+5
= 14 days.
c. The finish time for Task A is nine days. The ES for Task B is the same as the finish time
for Task A. The EF for Task B is the ES of Task B + Estimated Duration of Task B = 9+5
= 14 days.
d. The finish time for Task A is nine days. The ES for Task B is the same as the finish time
Copyright Cengage Learning. Powered by Cognero. Page 44Chapter 05
Gido & Clements
for Task A. The EF for Task B is the ES of Task B + Estimated Duration of Task B = 9+5
= 14 days.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.06 – 6. Prepare a project schedule
CTIVES:
NATIONAL STAN
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
71. The project control process involves all of the following except
a. regularly gathering data on project performance.
b. comparing actual performance to planned performance.
c. taking corrective action immediately if actual performance is behind planned performance.
d. having social gatherings with the project team.
ANSWER: d
FEEDBACK: a. The project control process involves regularly gathering data on project performance,
comparing actual performance to planned performance, and taking corrective action
immediately if actual performance is behind planned performance.
b. The project control process involves regularly gathering data on project performance,
comparing actual performance to planned performance, and taking corrective action
immediately if actual performance is behind planned performance.
c. The project control process involves regularly gathering data on project performance,
comparing actual performance to planned performance, and taking corrective action
immediately if actual performance is behind planned performance.
d. The project control process involves regularly gathering data on project performance,
comparing actual performance to planned performance, and taking corrective action
immediately if actual performance is behind planned performance.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.08 – 8. Discuss the project control process
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
Copyright Cengage Learning. Powered by Cognero. Page 45Chapter 05
Gido & Clements
KEYWORDS: Bloom’s: Analysis
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
72. The project control process must occur regularly throughout the project and include all of the following except
a. Record information on changes to the project scope, schedule, and budget.
b. Gather data on actual performance.
c. Having a single inspection of the project’s deliverables at the end of the project.
d. Establish regular reporting meetings to compare actual to planned progress.
ANSWER: c
FEEDBACK: a. The project control process must occur regularly throughout the project and also:Establish
regular reporting meetings to compare actual to planned progress.Gather data on actual
performance.Record information on changes to the project scope, schedule, and budget.
b. The project control process must occur regularly throughout the project and also:Establish
regular reporting meetings to compare actual to planned progress.Gather data on actual
performance.Record information on changes to the project scope, schedule, and budget.
c. The project control process must occur regularly throughout the project and also:Establish
regular reporting meetings to compare actual to planned progress.Gather data on actual
performance.Record information on changes to the project scope, schedule, and budget.
d. The project control process must occur regularly throughout the project and also:Establish
regular reporting meetings to compare actual to planned progress.Gather data on actual
performance.Record information on changes to the project scope, schedule, and budget.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.08 – 8. Discuss the project control process
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Analysis
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
73. The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and
regular basis and
a. taking any needed corrective action immediately.
b. leaving the project to self-correct.
c. fast tracking all the activities in the project until the project is ahead of schedule.
d. making sure the critical path doesn’t change.
Copyright Cengage Learning. Powered by Cognero. Page 46Chapter 05
Gido & Clements
ANSWER: a
FEEDBACK: a. The key to effective project control is measuring actual progress and comparing it to
planned progress on a timely and regular basis and taking any needed corrective action
immediately.
b. The key to effective project control is measuring actual progress and comparing it to
planned progress on a timely and regular basis and taking any needed corrective action
immediately.
c. The key to effective project control is measuring actual progress and comparing it to
planned progress on a timely and regular basis and taking any needed corrective action
immediately.
d. The key to effective project control is measuring actual progress and comparing it to
planned progress on a timely and regular basis and taking any needed corrective action
immediately.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.08 – 8. Discuss the project control process
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
74. With respect to the project schedule, changes can result in any of the following except
a. the addition or deletion of activities.
b. the initial planning and sequencing of activities.
c. changes to estimated durations for specific activities.
d. a new required completion time for the project.
ANSWER: b
Copyright Cengage Learning. Powered by Cognero. Page 47Chapter 05
Gido & Clements
FEEDBACK: a. With respect to the project schedule, changes can result in the addition or deletion of
activities, resequencing of activities, changes to estimated durations for specific activities,
or a new required completion time for the project.
b. With respect to the project schedule, changes can result in the addition or deletion of
activities, resequencing of activities, changes to estimated durations for specific activities,
or a new required completion time for the project.
c. With respect to the project schedule, changes can result in the addition or deletion of
activities, resequencing of activities, changes to estimated durations for specific activities,
or a new required completion time for the project.
d. With respect to the project schedule, changes can result in the addition or deletion of
activities, resequencing of activities, changes to estimated durations for specific activities,
or a new required completion time for the project.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.09 – 9. Develop updated schedules based on actual progress and changes
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
4/5/2016 10:13 AM
DATE MODIFIE
D:
75. If the planned corrective actions do not result in an acceptable schedule, then
a. b. c. d. the project should be terminated.
the steps for schedule control need to be repeated.
the original project plan was best and should be used.
the customer should decide what should be done.
ANSWER: b
FEEDBACK: a. If the planned corrective actions do not result in an acceptable schedule, these steps
need to be repeated.
b. If the planned corrective actions do not result in an acceptable schedule, these steps
need to be repeated.
c. If the planned corrective actions do not result in an acceptable schedule, these steps
need to be repeated.
d. If the planned corrective actions do not result in an acceptable schedule, these steps
need to be repeated.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: Multiple Choice
Copyright Cengage Learning. Powered by Cognero. Page 48Chapter 05
Gido & Clements
HAS VARIABLES: False
LEARNING OBJECTIV
ES:
SUPM.GIDO.15.05.10 – 10. Discuss and apply approaches to control the project schedule
NATIONAL STANDAR
United States – BUSPROG: Ethics
DS:
KEYWORDS: Bloom’s: Evaluation
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
76. A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that
a. are near term and those with long durations.
b. are short in duration and can be easily completed.
c. have the lowest cost.
d. are scheduled at the end of the project.
ANSWER: a
FEEDBACK: a. A concentrated effort to accelerate project progress must be applied to the paths with
negative slack to activities that are near term and those with long durations.
b. A concentrated effort to accelerate project progress must be applied to the paths with
negative slack to activities that are near term and those with long durations.
c. A concentrated effort to accelerate project progress must be applied to the paths with
negative slack to activities that are near term and those with long durations.
d. A concentrated effort to accelerate project progress must be applied to the paths with
negative slack to activities that are near term and those with long durations.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.10 – 10. Discuss and apply approaches to control the project schedule
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
77. Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of
a. no change in costs and an increase in scope.
b. a decrease in costs and an expansion in scope.
c. an increase in costs or a reduction in scope.
d. an decrease in costs and no change in scope.
ANSWER: c
Copyright Cengage Learning. Powered by Cognero. Page 49Chapter 05
Gido & Clements
FEEDBACK: a. Eliminating negative slack by reducing durations of activities will involve a trade-off in
the form of an increase in costs or a reduction in scope.
b. Eliminating negative slack by reducing durations of activities will involve a trade-off in
the form of an increase in costs or a reduction in scope.
c. Eliminating negative slack by reducing durations of activities will involve a trade-off in
the form of an increase in costs or a reduction in scope.
d. Eliminating negative slack by reducing durations of activities will involve a trade-off in
the form of an increase in costs or a reduction in scope.
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
SUPM.GIDO.15.05.10 – 10. Discuss and apply approaches to control the project schedule
NATIONAL STAN
DARDS:
United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED
4/5/2016 10:13 AM
:
78. Schedule control involves four steps. Place these steps in their proper order by stating the letter sequence of their
proper order.
A. Analyzing the schedule to determine which areas may need corrective action
B. Recalculating the schedule to evaluate the effects of the planned corrective actions
C. Revising the plan to incorporate the chosen corrective actions
D. Deciding what specific corrective actions should be taken
a. A,B,C,D
b. A,D,C,B
c. D,A,C,B
d. D,A,B,C
ANSWER: b
FEEDBACK: a. Schedule control involves four steps:
1. Analyzing the schedule to determine which areas may need corrective action
2. Deciding what specific corrective actions should be taken
3. Revising the plan to incorporate the chosen corrective actions
4. Recalculating the schedule to evaluate the effects of the planned corrective
actions
b. Schedule control involves four steps:
1. Analyzing the schedule to determine which areas may need corrective action
2. Deciding what specific corrective actions should be taken
3. Revising the plan to incorporate the chosen corrective actions
4. Recalculating the schedule to evaluate the effects of the planned corrective
actions
Copyright Cengage Learning. Powered by Cognero. Page 50Chapter 05
Gido & Clements
c. Schedule control involves four steps:
1. Analyzing the schedule to determine which areas may need corrective action
2. Deciding what specific corrective actions should be taken
3. Revising the plan to incorporate the chosen corrective actions
4. Recalculating the schedule to evaluate the effects of the planned corrective
actions
d. Schedule control involves four steps:
1. Analyzing the schedule to determine which areas may need corrective action
2. Deciding what specific corrective actions should be taken
3. Revising the plan to incorporate the chosen corrective actions
4. Recalculating the schedule to evaluate the effects of the planned corrective
actions
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.10 – 10. Discuss and apply approaches to control the project schedule
NATIONAL STANDARDS: United States – BUSPORG: Comprehension – BUSPORG:Comprehension
KEYWORDS: Bloom’s: Evaluation
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
79. Schedule control involves four steps. List the four steps in order.
ANSWER: Schedule control involves four steps:
1. Analyzing the schedule to determine which areas may need corrective action
2. Deciding what specific corrective actions should be taken
3. Revising the plan to incorporate the chosen corrective actions
4. Recalculating the schedule to evaluate the effects of the planned corrective actions
POINTS: 1
DIFFICULTY: Moderate
QUESTION TYPE: Subjective Short Answer
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.10 – 10. Discuss and apply approaches to control the project schedule
NATIONAL STANDARDS: United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
80. Agile project management is an approach to ____ product development time while ____ risk through continuous
interaction between the customer and small self-organizing teams that produce increments of working product.
a. reduce, minimizing
b. increase, maximizing
c. reduce, maximizing
d. increase, minimizing
ANSWER: a
Copyright Cengage Learning. Powered by Cognero. Page 51Chapter 05
Gido & Clements
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: NATIONAL STANDARDS: SUPM.GIDO.15.05.11 – 11. Explain agile project management
United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
81. The project team member also referred to as the customer representative and responsible for defining the customer
requirements and product features and for ensuring that the development team delivers an end product with the required
features is the
a. Scrum master.
b. project manager.
c. product owner.
d. sprint timer.
ANSWER: c
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.11 – 11. Explain agile project management
NATIONAL STANDARDS: United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 2/18/2017 2:46 PM
82. The development team develops, delivers, and demonstrates ____ during a sprint.
a. the entire product
b. working product increments
c. final team presentations and meeting agendas
d. only those products not contracted yet
ANSWER: b
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.11 – 11. Explain agile project management
NATIONAL STANDARDS: United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
Copyright Cengage Learning. Powered by Cognero. Page 52Chapter 05
Gido & Clements
83. As a part of the Scrum technique in agile project management, a sprint is usually one to four
a. days.
b. minutes.
c. weeks.
d. months.
ANSWER: c
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: NATIONAL STANDARDS: SUPM.GIDO.15.05.11 – 11. Explain agile project management
United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
84. The facilitator for the Scrum development process during a sprint whose primary job is to take actions to remove or
reduce any obstacles, barriers, or constraints that are impeding progress of the development team toward accomplishing
their work tasks and that may negatively impact the successful production and demonstration of a deliverable working
product increment by the end of the sprint time is the
a. Scrum master.
b. project manager.
c. product owner.
d. sprint timer.
ANSWER: a
POINTS: 1
DIFFICULTY: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.11 – 11. Explain agile project management
NATIONAL STANDARDS: United States – BUSPROG: Communications
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
85. The Scrum master is ____ as a project manager in that he ____ responsibility for the people on the development team.
a. the same, has indirect
b. the same, has direct
c. d. not the same, has direct
not the same, does not have direct
ANSWER: d
POINTS: 1
DIFFICULTY: Moderate
Copyright Cengage Learning. Powered by Cognero. Page 53Chapter 05
Gido & Clements
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.15.05.11 – 11. Explain agile project management
NATIONAL STANDARDS: United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIED: 4/5/2016 10:13 AM
86. Describe the agile project management for a project where a Scrum master is facilitating the Scrum development
process for a software development project. Include a description of the six steps in the agile project management process.
ANSWER: Answers will include the six steps of the agile project management process.
The agile project management process includes: a) establishing the rationale, description, funding
amount, and target completion date for the final end product (deliverable) and authorizing the project,
b) defining the product requirements and creating an ordered product backlog of prioritized specific
requirements and product features, c) having a sprint planning meeting and creating the sprint backlog
list, d) having a daily scrum meeting, also known as the daily standup and usually limited to 15
minutes, e) having a sprint review meeting at the end of the sprint, and f) having a sprint retrospective
meeting at the end of the sprint.
POINTS: 1
DIFFICULTY: Challenging
QUESTION TYPE
Subjective Short Answer
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.15.05.11 – 11. Explain agile project management
CTIVES:
NATIONAL STAN
United States – BUSPROG: Technology: Technology: – BUSPROG: Technology
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 4/5/2016 10:13 AM
DATE MODIFIE
D:
4/5/2016 10:13 AM
87. The overall window of time in which a project must be completed is defined by its ____ time and ____ time.
a. earliest start, earliest finish
b. latest start, latest finish
c. estimated start, required completion
d. critical, most critical
ANSWER: c
FEEDBACK: a.
The overall window of time in which a project must be completed is defined by its
estimated start time and required completion time.
b.
The overall window of time in which a project must be completed is defined by its
estimated start time and required completion time.
c.
The overall window of time in which a project must be completed is defined by its
estimated start time and required completion time.
Copyright Cengage Learning. Powered by Cognero. Page 54Chapter 05
Gido & Clements
d.
The overall window of time in which a project must be completed is defined by its
estimated start time and required completion time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJEC
SUPM.GIDO.18.05.03 – Determine the earliest start and finish times for activities
TIVES:
NATIONAL STAND
ARDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Evaluation
DATE CREATED: 2/18/2017 2:47 PM
DATE MODIFIED: 2/18/2017 2:49 PM
88. The ____ and ____ times are determined by calculating forward through the network.
a. ES, EF
b. LS, LF
c. ES, LS
d. EF, LF
ANSWER: a
FEEDBACK: a.
b.
c.
d.
The ES and EF times are determined by calculating forward through the
network.
The ES and EF times are determined by calculating forward through the
network.
The ES and EF times are determined by calculating forward through the
network.
The ES and EF times are determined by calculating forward through the
network.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.18.05.03 – Determine the earliest start and finish times for activities
NATIONAL STANDARDS: United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 2:50 PM
DATE MODIFIED: 2/18/2017 2:52 PM
89. Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 12, its other successor, Task E, has a latest start
on day 12, and the duration of Task D is 2 days.
a. day 14
b. day 10
c. day 12
d. cannot be calculated based upon information given.
Copyright Cengage Learning. Powered by Cognero. Page 55Chapter 05
Gido & Clements
ANSWER: b
FEEDBACK: a.
b.
c.
d.
Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS
=
LF– Estimated Duration.
Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS
=
LF– Estimated Duration.
Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS
=
LF– Estimated Duration.
Latest start time is calculated by subtracting the activity’s estimated duration from the
activity’s latest finish time: LS
=
LF– Estimated Duration.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
NATIONAL STAN
DARDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Analysis
DATE CREATED: 2/18/2017 2:54 PM
DATE MODIFIED
2/18/2017 2:59 PM
:
SUPM.GIDO.18.05.04 – Determine the latest start and finish times for activities
90. Earliest finish time (EF) is calculated ____.
a. by dividing the activity’s latest finish time by the activity’s earliest start time.
b. by multiplying the activity’s duration estimate with the activity’s latest finish time.
c. by adding the activity’s duration estimate to the activity’s earliest start time.
d. by subtracting the activity’s duration estimate from the activity’s latest finish time.
ANSWER: c
FEEDBACK: a.
b.
c.
d.
Earliest finish time (EF) is calculated by adding the activity’s duration estimate to the
activity’s earliest start time
Earliest finish time (EF) is calculated by adding the activity’s duration estimate to the
activity’s earliest start time
Earliest finish time (EF) is calculated by adding the activity’s duration estimate to the
activity’s earliest start time
Earliest finish time (EF) is calculated by adding the activity’s duration estimate to the
activity’s earliest start time
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTI
VES:
NATIONAL STANDAR
United States – BUSPROG: Analytic
DS:
KEYWORDS: Bloom’s: Analysis
Copyright Cengage Learning. Powered by Cognero. SUPM.GIDO.18.05.03 – Determine the earliest start and finish times for activities
Page 56Chapter 05
Gido & Clements
DATE CREATED: 2/18/2017 2:52 PM
DATE MODIFIED: 2/18/2017 2:53 PM
91. ____ time is the latest time by which a particular activity must be finished in order for the entire project to be
completed by its required completion time.
a. Earliest start
b. Earliest finish
c. Latest start
d. Latest finish
ANSWER: d
FEEDBACK: a.
b.
c.
d.
Latest finish time is the latest time by which a particular activity must be finished in order
for the entire project to be completed by its required completion time.
Latest finish time is the latest time by which a particular activity must be finished in order
for the entire project to be completed by its required completion time.
Latest finish time is the latest time by which a particular activity must be finished in order
for the entire project to be completed by its required completion time.
Latest finish time is the latest time by which a particular activity must be finished in order
for the entire project to be completed by its required completion time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.04 – Determine the latest start and finish times for activities
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 2:59 PM
DATE MODIFIE
D:
2/18/2017 3:02 PM
92. The ____ and ____ times are determined by working through the network diagram from the end of the project to the
beginning of the project.
a. ES, EF
b. LF, LS
c. ES, LS
d. EF, LF
ANSWER: b
FEEDBACK: a.
b.
c.
The LF and LS times are determined by working through the network diagram from the
end of the project to the beginning of the project.
The LF and LS times are determined by working through the network diagram from the
end of the project to the beginning of the project.
The LF and LS times are determined by working through the network diagram from the
Copyright Cengage Learning. Powered by Cognero. Page 57Chapter 05
Gido & Clements
d.
end of the project to the beginning of the project.
The LF and LS times are determined by working through the network diagram from the
end of the project to the beginning of the project.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
NATIONAL STAN
DARDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:02 PM
DATE MODIFIED: 2/18/2017 3:04 PM
SUPM.GIDO.18.05.04 – Determine the latest start and finish times for activities
93. If ____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed
without jeopardizing completion of the project by its required completion time.
a. total time
b. free time
c. total slack
d. cumulative slack
ANSWER: c
FEEDBACK: a.
b.
c.
d.
If total slack is positive, it represents the maximum amount of time that the activities on a
particular path can be delayed without jeopardizing completion of the project by its
required completion time.
If total slack is positive, it represents the maximum amount of time that the activities on a
particular path can be delayed without jeopardizing completion of the project by its
required completion time.
If total slack is positive, it represents the maximum amount of time that the activities on a
particular path can be delayed without jeopardizing completion of the project by its
required completion time.
If total slack is positive, it represents the maximum amount of time that the activities on a
particular path can be delayed without jeopardizing completion of the project by its
required completion time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.05 – Explain and determine total slack
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Evaluation
Copyright Cengage Learning. Powered by Cognero. Page 58Chapter 05
Gido & Clements
DATE CREATED: 2/18/2017 3:04 PM
DATE MODIFIE
D:
2/18/2017 3:06 PM
94. Total slack is calculated by ____.
a. subtracting the activity’s duration estimate from the activity’s latest finish time
b. adding the activity’s duration estimate to the activity’s earliest start time
c. finding the relative difference between values of free slack for activities entering into the same activity.
d. subtracting the activity’s earliest finish (or start) time from its latest finish (or start) time.
ANSWER: d
FEEDBACK: a.
b.
c.
d.
Total slack is calculated by subtracting the activity’s earliest finish (or start) time from
its latest finish (or start) time.
Total slack is calculated by subtracting the activity’s earliest finish (or start) time from
its latest finish (or start) time.
Total slack is calculated by subtracting the activity’s earliest finish (or start) time from
its latest finish (or start) time.
Total slack is calculated by subtracting the activity’s earliest finish (or start) time from
its latest finish (or start) time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTI
SUPM.GIDO.18.05.05 – Explain and determine total slack
VES:
NATIONAL STANDA
RDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Evaluation
DATE CREATED: 2/18/2017 3:06 PM
DATE MODIFIED: 2/18/2017 3:08 PM
95.
a. Truncation
b. Looping
c. Laddering
d. Transitions
ANSWER: c
FEEDBACK: a. Laddering can sometimes be used for projects that have a set of activities that are
repeated several times.
b. Laddering can sometimes be used for projects that have a set of activities that are
repeated several times.
c. Laddering can sometimes be used for projects that have a set of activities that are
repeated several times.
d. Laddering can sometimes be used for projects that have a set of activities that are
repeated several times.
POINTS: 1
Copyright Cengage Learning. Powered by Cognero. Page 59Chapter 05
Gido & Clements
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIV
SUPM.GIDO.18.05.06 – Prepare a project schedule
ES:
NATIONAL STANDAR
DS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:08 PM
DATE MODIFIED: 2/18/2017 3:13 PM
96.
a. software planner
b. systems development life cycle
c. software development learning curve
d. systems development life circle
ANSWER: b
FEEDBACK: a.
b.
c.
d.
A project management planning tool, or methodology, called the systems development life
cycle is often used to help plan, execute, and control IS development projects.
A project management planning tool, or methodology, called the systems development life
cycle is often used to help plan, execute, and control IS development projects.
A project management planning tool, or methodology, called the systems development life
cycle is often used to help plan, execute, and control IS development projects.
A project management planning tool, or methodology, called the systems development life
cycle is often used to help plan, execute, and control IS development projects.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.06 – Prepare a project schedule
CTIVES:
NATIONAL STAN
United States – BUSPROG: Reflective Thinking
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:10 PM
DATE MODIFIE
D:
2/18/2017 3:12 PM
97.
a. Problem definition
b. System analysis
c. System design
Copyright Cengage Learning. Powered by Cognero. Page 60Chapter 05
Gido & Clements
d. System development
ANSWER: a
FEEDBACK: a. During the Problem definition phase of the SDLC is data gathered and analyzed, and
problems and opportunities clearly defined.
b. During the Problem definition phase of the SDLC is data gathered and analyzed, and
problems and opportunities clearly defined.
c. During the Problem definition phase of the SDLC is data gathered and analyzed, and
problems and opportunities clearly defined.
d. During the Problem definition phase of the SDLC is data gathered and analyzed, and
problems and opportunities clearly defined.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJEC
TIVES:
SUPM.GIDO.18.05.06 – Prepare a project schedule
NATIONAL STAND
ARDS:
United States – BUSPROG: Reflective Thinking
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:13 PM
DATE MODIFIED: 2/18/2017 3:14 PM
98.
During which phase of the SDLC does the development team define the scope of the system to be developed,
interview potential users, study the existing system, and define user requirements?
a. Problem definition
b. System analysis
c. System design
d. System development
ANSWER: b
FEEDBACK: a. During the System analysis phase of the SDLC does the development team define the
scope of the system to be developed, interview potential users, study the existing system,
and define user requirements.
b. During the System analysis phase of the SDLC does the development team define the
scope of the system to be developed, interview potential users, study the existing system,
and define user requirements.
c. During the System analysis phase of the SDLC does the development team define the
scope of the system to be developed, interview potential users, study the existing system,
and define user requirements.
d. During the System analysis phase of the SDLC does the development team define the
scope of the system to be developed, interview potential users, study the existing system,
and define user requirements.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
Copyright Cengage Learning. Powered by Cognero. Page 61Chapter 05
Gido & Clements
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.06 – Prepare a project schedule
CTIVES:
NATIONAL STAN
United States – BUSPROG: Reflective Thinking
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:15 PM
DATE MODIFIE
D:
2/18/2017 3:18 PM
99.
a. System analysis
b. System design
c. System development
d. System implementation
ANSWER: c
FEEDBACK: a. During the System development phase of the SDLC is hardware purchased, while
software is purchased, customized, or developed
b. During the System development phase of the SDLC is hardware purchased, while
software is purchased, customized, or developed
c. During the System development phase of the SDLC is hardware purchased, while
software is purchased, customized, or developed
d. During the System development phase of the SDLC is hardware purchased, while
software is purchased, customized, or developed
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJEC
SUPM.GIDO.18.05.06 – Prepare a project schedule
TIVES:
NATIONAL STAND
ARDS:
United States – BUSPROG: Reflective Thinking
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:18 PM
DATE MODIFIED: 2/18/2017 3:19 PM
100.
a. A schedule
b. An objective
c. An activity
d. A network
ANSWER: a
Copyright Cengage Learning. Powered by Cognero. Page 62Chapter 05
Gido & Clements
FEEDBACK: a.
b.
c.
d.
A schedule is a timetable for a plan and, therefore, cannot be established until the
plan has been developed.
A schedule is a timetable for a plan and, therefore, cannot be established until the
plan has been developed.
A schedule is a timetable for a plan and, therefore, cannot be established until the
plan has been developed.
A schedule is a timetable for a plan and, therefore, cannot be established until the
plan has been developed.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTI
VES:
SUPM.GIDO.18.05.06 – Prepare a project schedule
NATIONAL STANDAR
DS:
United States – BUSPROG: Reflective Thinking
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:20 PM
DATE MODIFIED: 2/18/2017 3:25 PM
101.
a. value
b. noncritical
c. critical
d. float
ANSWER: c
FEEDBACK: a.
b.
c.
d.
The longest path of activities from the beginning to the end of a project is called the
critical path..
The longest path of activities from the beginning to the end of a project is called the
critical path..
The longest path of activities from the beginning to the end of a project is called the
critical path..
The longest path of activities from the beginning to the end of a project is called the
critical path..
POINTS: 1
DIFFICULTY: Difficulty: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVE
SUPM.GIDO.18.05.07 – Identify and explain the critical path
S:
NATIONAL STANDARD
United States – BUSPROG: Communication – Communication
S:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 2/18/2017 3:22 PM
DATE MODIFIED: 2/18/2017 3:23 PM
Copyright Cengage Learning. Powered by Cognero. Page 63Chapter 05
Gido & Clements
102.
a. normal
b. beta
c. float
d. noncritical
ANSWER: d
FEEDBACK: a.
b.
c.
d.
Those paths with positive values of total slack are sometimes referred to as
noncritical paths
Those paths with positive values of total slack are sometimes referred to as
noncritical paths
Those paths with positive values of total slack are sometimes referred to as
noncritical paths
Those paths with positive values of total slack are sometimes referred to as
noncritical paths
POINTS: 1
DIFFICULTY: Difficulty: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVE
SUPM.GIDO.18.05.07 – Identify and explain the critical path
S:
NATIONAL STANDARDS
United States – BUSPROG: Communication – Communication
:
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 2/18/2017 3:26 PM
DATE MODIFIED: 2/18/2017 3:28 PM
103.
a. Free time
b. Free slack
c. Free change
d. Work release
ANSWER: b
FEEDBACK: a.
b.
c.
d.
Free slack is the amount of time a particular activity can be delayed without delaying the
earliest start time of its immediately succeeding activities.
Free slack is the amount of time a particular activity can be delayed without delaying the
earliest start time of its immediately succeeding activities.
Free slack is the amount of time a particular activity can be delayed without delaying the
earliest start time of its immediately succeeding activities.
Free slack is the amount of time a particular activity can be delayed without delaying the
earliest start time of its immediately succeeding activities.
POINTS: 1
DIFFICULTY: Difficulty: Easy
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
Copyright Cengage Learning. Powered by Cognero. Page 64Chapter 05
Gido & Clements
LEARNING OBJE
CTIVES:
SUPM.GIDO.18.05.07 – Identify and explain the critical path
NATIONAL STAN
DARDS:
United States – BUSPROG: Communication – Communication
KEYWORDS: Bloom’s: Knowledge
DATE CREATED: 2/18/2017 3:28 PM
DATE MODIFIE
D:
104.
2/18/2017 3:30 PM
a. pessimistic
b. optimal
c. most likely
d. optimistic
ANSWER: c
FEEDBACK: a.
b.
c.
d.
If an activity has been repeated many times, the actual duration that occurs most
frequently can be used as the most likely time estimate.
If an activity has been repeated many times, the actual duration that occurs most
frequently can be used as the most likely time estimate.
If an activity has been repeated many times, the actual duration that occurs most
frequently can be used as the most likely time estimate.
If an activity has been repeated many times, the actual duration that occurs most
frequently can be used as the most likely time estimate.
POINTS: 1
DIFFICULTY: Difficulty: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
NATIONAL STAN
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 3:30 PM
DATE MODIFIED
2/18/2017 3:32 PM
:
SUPM.GIDO.18.05.07 – Identify and explain the critical path
United States – BUSPROG: Communication – Communication
105.
a. bell
b. beta
c. random
d. normal
ANSWER: b
FEEDBACK: a.
In network planning, when three time estimates are used for each activity, it is assumed
that the three estimates follow a beta probability distribution.
Copyright Cengage Learning. Powered by Cognero. Page 65Chapter 05
Gido & Clements
b.
c.
d.
In network planning, when three time estimates are used for each activity, it is assumed
that the three estimates follow a beta probability distribution.
In network planning, when three time estimates are used for each activity, it is assumed
that the three estimates follow a beta probability distribution.
In network planning, when three time estimates are used for each activity, it is assumed
that the three estimates follow a beta probability distribution.
POINTS: 1
DIFFICULTY: Difficulty: Easy
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.07 – Identify and explain the critical path
CTIVES:
NATIONAL STAN
United States – BUSPROG: Communication – Communication
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:32 PM
DATE MODIFIE
D:
2/18/2017 3:35 PM
106.
a. deterministic
b. stochastic
c. probabilistic
d. random
ANSWER: a
FEEDBACK: a. Any technique that uses only one time estimate is considered to be a deterministic
technique.
b. Any technique that uses only one time estimate is considered to be a deterministic
technique.
c. Any technique that uses only one time estimate is considered to be a deterministic
technique.
d. Any technique that uses only one time estimate is considered to be a deterministic
technique.
POINTS: 1
DIFFICULTY: Difficulty: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVE
S:
:
SUPM.GIDO.18.05.07 – Identify and explain the critical path
NATIONAL STANDARDS
United States – BUSPROG: Communication – Communication
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:35 PM
Copyright Cengage Learning. Powered by Cognero. Page 66Chapter 05
Gido & Clements
DATE MODIFIED: 2/18/2017 3:37 PM
107. The ____ involves regularly gathering data on project performance, comparing actual performance to planned
performance, and taking corrective actions if actual performance is behind planned performance.
a. rational unified process
b. project control process
c. network-based planning process
d. work breakdown structure
ANSWER: b
FEEDBACK: a.
b.
c.
d.
The project control process involves regularly gathering data on project performance,
comparing actual performance to planned performance, and taking corrective actions if
actual performance is behind planned performance.
The project control process involves regularly gathering data on project performance,
comparing actual performance to planned performance, and taking corrective actions if
actual performance is behind planned performance.
The project control process involves regularly gathering data on project performance,
comparing actual performance to planned performance, and taking corrective actions if
actual performance is behind planned performance.
The project control process involves regularly gathering data on project performance,
comparing actual performance to planned performance, and taking corrective actions if
actual performance is behind planned performance.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.08 – Discuss the project control process
CTIVES:
NATIONAL STAN
United States – BUSPROG: Reflective Thinking
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:37 PM
DATE MODIFIE
D:
2/18/2017 3:39 PM
108. The project control process starts with establishing a ____.
a. baseline plan
b. work order form
c. schedule assignments
d. time-cost tradeoff
ANSWER: a
Copyright Cengage Learning. Powered by Cognero. Page 67Chapter 05
Gido & Clements
FEEDBACK: a.
b.
c.
d.
The project control process starts with establishing a baseline plan
The project control process starts with establishing a baseline plan
The project control process starts with establishing a baseline plan
The project control process starts with establishing a baseline plan
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.18.05.08 – Discuss the project control process
NATIONAL STANDARDS: United States – BUSPROG: Reflective Thinking
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:39 PM
DATE MODIFIED: 2/18/2017 3:40 PM
109. The ____ of completed activities will determine the earliest start and earliest finish times for the remaining activities
in the network diagram, as well as the total slack.
a. actual finish times
b. finish estimates
c. actual efficiency ratios
d. actual resource shares
ANSWER: a
FEEDBACK: a.
b.
c.
d.
The actual finish times of completed activities will determine the earliest start and earliest
finish times for the remaining activities in the network diagram, as well as the total slack
The actual finish times of completed activities will determine the earliest start and earliest
finish times for the remaining activities in the network diagram, as well as the total slack
The actual finish times of completed activities will determine the earliest start and earliest
finish times for the remaining activities in the network diagram, as well as the total slack
The actual finish times of completed activities will determine the earliest start and earliest
finish times for the remaining activities in the network diagram, as well as the total slack
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.09 – Develop updated schedules based on actual progress and changes
CTIVES:
NATIONAL STAN
United States – BUSPROG: Reflective Thinking
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:41 PM
DATE MODIFIE
D:
2/18/2017 3:43 PM
Copyright Cengage Learning. Powered by Cognero. Page 68Chapter 05
Gido & Clements
110. In most cases, eliminating negative slack by reducing durations of activities will involve a trade-off in the form of an
increase in ____ or a reduction in ____.
a. production hours, budget
b. costs, scope
c. scope, costs
d. scope, production hours
ANSWER: b
FEEDBACK: a.
b.
c.
d.
In most cases, eliminating negative slack by reducing durations of activities will involve a
trade-off in the form of an increase in costs or a reduction in scope
In most cases, eliminating negative slack by reducing durations of activities will involve a
trade-off in the form of an increase in costs or a reduction in scope
In most cases, eliminating negative slack by reducing durations of activities will involve a
trade-off in the form of an increase in costs or a reduction in scope
In most cases, eliminating negative slack by reducing durations of activities will involve a
trade-off in the form of an increase in costs or a reduction in scope
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:45 PM
DATE MODIFIE
D:
2/18/2017 3:47 PM
111. A regular ____ should be established for comparing actual progress with planned progress.
a. work breakdown assignment chart
b. time-cost tradeoff analysis
c. printout evaluation
d. reporting period
ANSWER: d
FEEDBACK: a.
b.
c.
d.
A regular reporting period should be established for comparing actual progress with
planned progress.
A regular reporting period should be established for comparing actual progress with
planned progress.
A regular reporting period should be established for comparing actual progress with
planned progress.
A regular reporting period should be established for comparing actual progress with
planned progress.
POINTS: 1
Copyright Cengage Learning. Powered by Cognero. Page 69Chapter 05
Gido & Clements
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIV
ES:
SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
NATIONAL STANDAR
DS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:48 PM
DATE MODIFIED: 2/18/2017 3:50 PM
112. When changes are agreed upon, a new ____ should be established and used as the benchmark against which actual
project performance will be compared.
a. time-cost diagram
b. baseline plan
c. work expectations form
d. management matrix
ANSWER: b
FEEDBACK: a.
b.
c.
d.
When changes are agreed upon, a new baseline plan should be established and used as
the benchmark against which actual project performance will be compared.
When changes are agreed upon, a new baseline plan should be established and used as
the benchmark against which actual project performance will be compared.
When changes are agreed upon, a new baseline plan should be established and used as
the benchmark against which actual project performance will be compared.
When changes are agreed upon, a new baseline plan should be established and used as
the benchmark against which actual project performance will be compared.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:50 PM
DATE MODIFIE
D:
2/18/2017 3:52 PM
113. The amount of ____ should determine the priority with which concentrated efforts are applied.
a. actual progress
b. work breakdown structure
c. time spent
Copyright Cengage Learning. Powered by Cognero. Page 70Chapter 05
Gido & Clements
d. slack
ANSWER: d
FEEDBACK: a.
b.
c.
d.
The amount of slack should determine the priority with which concentrated efforts
are applied.
The amount of slack should determine the priority with which concentrated efforts
are applied.
The amount of slack should determine the priority with which concentrated efforts
are applied.
The amount of slack should determine the priority with which concentrated efforts
are applied.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVE
S:
NATIONAL STANDARDS
United States – BUSPROG: Analytic
:
SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:52 PM
DATE MODIFIED: 2/18/2017 3:54 PM
114. The ____ trade-off methodology is used to incrementally reduce the project duration with the smallest associated
increase in incremental cost.
a. schedule-quality
b. cost-production
c. time-quality
d. time–cost
ANSWER: d
FEEDBACK: a.
b.
c.
d.
The time–cost trade-off methodology is used to incrementally reduce the project duration
with the smallest associated increase in incremental cost
The time–cost trade-off methodology is used to incrementally reduce the project duration
with the smallest associated increase in incremental cost
The time–cost trade-off methodology is used to incrementally reduce the project duration
with the smallest associated increase in incremental cost
The time–cost trade-off methodology is used to incrementally reduce the project duration
with the smallest associated increase in incremental cost
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
NATIONAL STAN United States – BUSPROG: Analytic
Copyright Cengage Learning. Powered by Cognero. SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
Page 71Chapter 05
Gido & Clements
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:54 PM
DATE MODIFIE
D:
2/18/2017 3:56 PM
115. Each activity has two pairs of duration and cost estimates: ____ and ____.
a. normal and crash
b. normal and flash
c. actual and crash
d. flash and level
ANSWER: a
FEEDBACK: a.
b.
c.
d.
Each activity has two pairs of duration and cost estimates: normal and crash
Each activity has two pairs of duration and cost estimates: normal and crash
Each activity has two pairs of duration and cost estimates: normal and crash
Each activity has two pairs of duration and cost estimates: normal and crash
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
NATIONAL STANDARDS: United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:56 PM
DATE MODIFIED: 2/18/2017 3:58 PM
116. The ____ time is the shortest estimated length of time in which the activity can be completed.
a. flash
b. level
c. crash
d. normal
ANSWER: c
FEEDBACK: a.
b.
c.
d.
The crash time is the shortest estimated length of time in which the activity can be
completed.
The crash time is the shortest estimated length of time in which the activity can be
completed.
The crash time is the shortest estimated length of time in which the activity can be
completed.
The crash time is the shortest estimated length of time in which the activity can be
completed.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
Copyright Cengage Learning. Powered by Cognero. Page 72Chapter 05
Gido & Clements
HAS VARIABLES: False
LEARNING OBJECTIVE
SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
S:
NATIONAL STANDARDS
United States – BUSPROG: Analytic
:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 3:58 PM
DATE MODIFIED: 2/18/2017 4:00 PM
117. The ____ is the estimated cost to complete the activity in the crash time.
a. opportunity cost
b. path cost
c. crash cost
d. normal cost
ANSWER: c
FEEDBACK: a.
b.
c.
d.
The crash cost is the estimated cost to complete the activity in the crash time.
The crash cost is the estimated cost to complete the activity in the crash time.
The crash cost is the estimated cost to complete the activity in the crash time.
The crash cost is the estimated cost to complete the activity in the crash time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
NATIONAL STANDARDS: United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 4:00 PM
DATE MODIFIED: 2/18/2017 4:01 PM
118. The ____ is the estimated cost to complete the activity in the normal time.
a. normal cost
b. path cost
c. crash cost
d. opportunity cost
ANSWER: a
FEEDBACK: a.
b.
c.
d.
The normal cost is the estimated cost to complete the activity in the normal time.
The normal cost is the estimated cost to complete the activity in the normal time.
The normal cost is the estimated cost to complete the activity in the normal time.
The normal cost is the estimated cost to complete the activity in the normal time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
Copyright Cengage Learning. Powered by Cognero. Page 73Chapter 05
Gido & Clements
LEARNING OBJECTIVES: SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
NATIONAL STANDARDS: United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 4:02 PM
DATE MODIFIED: 2/18/2017 4:02 PM
119. When planning the project, it is important to
a. determine all the details for all activities in the project.
b. estimate the types and quantities of resources required to perform each specific activity.
c. calculate the contingencies so that no changes will need to be made.
d. identify the names of the resources for every task to enter into the project management information system.
ANSWER: b
FEEDBACK: a.
b.
c.
d.
When planning the project, it is important to estimate the types and quantities of
resources required to perform each specific activity.
When planning the project, it is important to estimate the types and quantities of
resources required to perform each specific activity.
When planning the project, it is important to estimate the types and quantities of
resources required to perform each specific activity.
When planning the project, it is important to estimate the types and quantities of
resources required to perform each specific activity.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJEC
SUPM.GIDO.18.05.01 – Estimate the resources required for activities
TIVES:
NATIONAL STAND
ARDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 4:52 PM
DATE MODIFIED: 2/18/2017 4:55 PM
120. The duration of a task is
a. the total elapsed time for the activity.
b. the total time of all the work to be completed for the activity for all the resources.
c. the time estimated for the project divided by the number of activities.
d. the waiting time for the activity.
ANSWER: a
FEEDBACK: a.
b.
c.
d.
The duration of a task is the total elapsed time for the activity.
The duration of a task is the total elapsed time for the activity.
The duration of a task is the total elapsed time for the activity.
The duration of a task is the total elapsed time for the activity.
POINTS: 1
Copyright Cengage Learning. Powered by Cognero. Page 74Chapter 05
Gido & Clements
DIFFICULTY: Difficulty: Easy
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.18.05.01 – Estimate the resources required for activities
NATIONAL STANDARDS: United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 4:55 PM
DATE MODIFIED: 2/18/2017 4:57 PM
121. At the beginning of a longer-term project, it is easier to estimate the duration of
a. long duration activities.
b. all the activities of the project.
c.
near-term activities.
d.
short duration activities.
ANSWER: c
FEEDBACK: a.
b.
c.
d.
At the beginning of a longer-term project, it is easier to estimate the duration of near-
term activities.
At the beginning of a longer-term project, it is easier to estimate the duration of near-
term activities.
At the beginning of a longer-term project, it is easier to estimate the duration of near-
term activities.
At the beginning of a longer-term project, it is easier to estimate the duration of near-
term activities.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIV
ES:
SUPM.GIDO.18.05.01 – Estimate the resources required for activities
NATIONAL STANDARD
United States – BUSPROG: Analytic
S:
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 4:57 PM
DATE MODIFIED: 2/18/2017 4:59 PM
122. The earliest start time for an activity is
a. the date that all the resources for the project are available.
b. calculated using the project start time and the estimated duration of all of its preceding activities.
c. cannot be earlier than estimated, even if some activities are accelerated.
d. should not be delayed or would cause the project to be delayed.
ANSWER: b
Copyright Cengage Learning. Powered by Cognero. Page 75Chapter 05
Gido & Clements
FEEDBACK: a.
b.
c.
d.
The earliest start time for an activity is calculated using the project start time and the
estimated duration of all of its preceding activities.
The earliest start time for an activity is calculated using the project start time and the
estimated duration of all of its preceding activities.
The earliest start time for an activity is calculated using the project start time and the
estimated duration of all of its preceding activities.
The earliest start time for an activity is calculated using the project start time and the
estimated duration of all of its preceding activities.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
SUPM.GIDO.18.05.01 – Estimate the resources required for activities
NATIONAL STAND
United States – BUSPROG: Analytic
ARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 4:59 PM
DATE MODIFIED: 2/18/2017 5:01 PM
123. The earliest finish time for an activity
a. is calculated by adding the activity’s estimated duration to its earliest start time.
b. is the same as the earliest start time of the activity’s predecessor.
c. should not be delayed or would cause the project to be delayed.
d. is dependent upon the start time of its successor activities.
ANSWER: a
FEEDBACK: a.
b.
c.
d.
The earliest finish time for an activity is calculated by adding the activity’s estimated
duration to its earliest start time.
The earliest finish time for an activity is calculated by adding the activity’s estimated
duration to its earliest start time.
The earliest finish time for an activity is calculated by adding the activity’s estimated
duration to its earliest start time.
The earliest finish time for an activity is calculated by adding the activity’s estimated
duration to its earliest start time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTI
SUPM.GIDO.18.05.02 – Estimate the duration for an activity
VES:
NATIONAL STANDA
RDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 5:01 PM
DATE MODIFIED: 2/18/2017 5:04 PM
Copyright Cengage Learning. Powered by Cognero. Page 76Chapter 05
Gido & Clements
124. The latest finish time of a specific activity is
a. always equal to the activity’s earliest finish time.
b. the same as the latest start time of the activity’s predecessors.
c. the latest time the activity can be completed without delaying the project.
d. based upon the project start time and the activity durations.
ANSWER: c
FEEDBACK: a.
b.
c.
d.
The latest finish time of a specific activity is the latest time the activity can be
completed without delaying the project.
The latest finish time of a specific activity is the latest time the activity can be
completed without delaying the project.
The latest finish time of a specific activity is the latest time the activity can be
completed without delaying the project.
The latest finish time of a specific activity is the latest time the activity can be
completed without delaying the project.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTI
SUPM.GIDO.18.05.04 – Determine the latest start and finish times for activities
VES:
NATIONAL STANDA
RDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 5:04 PM
DATE MODIFIED: 2/18/2017 5:06 PM
125. The latest start time for a specific activity is
a. the latest time the activity can be started for the project to be completed on time.
b. always equal to the activity’s earliest finish time.
c. dependent upon the predecessor’s latest finish time.
d. same as the latest finish time of the activity’s successor activities.
ANSWER: a
FEEDBACK: a.
b.
c.
d.
The latest start time for a specific activity is the latest time the activity can be started for
the project to be completed on time.
The latest start time for a specific activity is the latest time the activity can be started for
the project to be completed on time.
The latest start time for a specific activity is the latest time the activity can be started for
the project to be completed on time.
The latest start time for a specific activity is the latest time the activity can be started for
the project to be completed on time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
Copyright Cengage Learning. Powered by Cognero. Page 77Chapter 05
Gido & Clements
LEARNING OBJEC
TIVES:
NATIONAL STAND
ARDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 5:06 PM
DATE MODIFIED: 2/18/2017 5:08 PM
SUPM.GIDO.18.05.04 – Determine the latest start and finish times for activities
126. Total slack for a project that is negative represents the amount of time that
a. the activities on the path can be delayed and the project still be completed on time
b. all the activities must be accelerated for the project to be completed on time.
c. all the activities can be delayed and the project still be completed on time.
d. the activities on the path must be accelerated for the project to be completed on time.
ANSWER: d
FEEDBACK: a.
b.
c.
d.
Total slack for a project that is negative represents the amount of time that the activities on
the path must be accelerated for the project to be completed on time.
Total slack for a project that is negative represents the amount of time that the activities on
the path must be accelerated for the project to be completed on time.
Total slack for a project that is negative represents the amount of time that the activities on
the path must be accelerated for the project to be completed on time.
Total slack for a project that is negative represents the amount of time that the activities on
the path must be accelerated for the project to be completed on time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.05 – Explain and determine total slack
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Comprehension
DATE CREATED: 2/18/2017 5:08 PM
DATE MODIFIE
D:
2/18/2017 5:11 PM
127. If the total slack for a project is 4 days, this means
a. the activities on the path can be delayed a total of four days and the project still could be completed on time.
b. the activities on the path must be accelerated by four days for the project to be completed on time.
c. all the activities must be accelerated by four days for the project to be completed on time.
d. all the activities can be delayed by four days and the project still be completed on time.
ANSWER: a
Copyright Cengage Learning. Powered by Cognero. Page 78Chapter 05
Gido & Clements
FEEDBACK: a.
b.
c.
d.
If the total slack for a project is 4 days, this means the activities on the path can be
delayed a total of four days and the project still could be completed on time.
If the total slack for a project is 4 days, this means the activities on the path can be
delayed a total of four days and the project still could be completed on time.
If the total slack for a project is 4 days, this means the activities on the path can be
delayed a total of four days and the project still could be completed on time.
If the total slack for a project is 4 days, this means the activities on the path can be
delayed a total of four days and the project still could be completed on time.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.05 – Explain and determine total slack
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Analysis
DATE CREATED: 2/18/2017 5:11 PM
DATE MODIFIE
D:
2/18/2017 5:16 PM
128. The critical path of a project
a. b. c. d. cannot change once the project has started.
is the longest path in the overall network diagram.
always has a negative slack.
always has a positive slack.
ANSWER: b
FEEDBACK: a.
b.
c.
d.
The critical path of a project is the longest path in the overall network diagram.
The critical path of a project is the longest path in the overall network diagram.
The critical path of a project is the longest path in the overall network diagram.
The critical path of a project is the longest path in the overall network diagram.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIVES: SUPM.GIDO.18.05.07 – Identify and explain the critical path
NATIONAL STANDARDS: United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 5:22 PM
DATE MODIFIED: 2/18/2017 5:25 PM
129. Free slack of an activity is
Copyright Cengage Learning. Powered by Cognero. Page 79Chapter 05
Gido & Clements
a. the slack on activities that do not have any costs associated with them.
b. can be calculated on every activity with a serial relationship to its successors.
c. the amount of time an activity can be postponed and not delay the start of its immediately succeeding activities.
d. is always a negative value.
ANSWER: c
FEEDBACK: a.
b.
c.
d.
Free slack of an activity is the amount of time an activity can be postponed and not delay
the start of its immediately succeeding activities.
Free slack of an activity is the amount of time an activity can be postponed and not delay
the start of its immediately succeeding activities.
Free slack of an activity is the amount of time an activity can be postponed and not delay
the start of its immediately succeeding activities.
Free slack of an activity is the amount of time an activity can be postponed and not delay
the start of its immediately succeeding activities.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
SUPM.GIDO.18.05.05 – Explain and determine total slack
NATIONAL STAN
DARDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 5:25 PM
DATE MODIFIED
2/18/2017 5:27 PM
:
130. The activity bars in a bar chart are drawn in proportion to
a. the amount of slack for each activity.
b. the number of resources assigned to the activity.
c. the cost of the activity.
d. the estimated durations of each activity.
ANSWER: d
FEEDBACK: a.
b.
c.
d.
The activity bars in a bar chart are drawn in proportion to the estimated durations of
each activity.
The activity bars in a bar chart are drawn in proportion to the estimated durations of
each activity.
The activity bars in a bar chart are drawn in proportion to the estimated durations of
each activity.
The activity bars in a bar chart are drawn in proportion to the estimated durations of
each activity.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
Copyright Cengage Learning. Powered by Cognero. Page 80Chapter 05
Gido & Clements
LEARNING OBJECTIVE
SUPM.GIDO.18.05.06 – Prepare a project schedule
S:
NATIONAL STANDARD
United States – BUSPROG: Analytic
S:
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 5:27 PM
DATE MODIFIED: 2/18/2017 5:29 PM
131. To control the project, the project team should collect
a. data on the actual performance and information about any changes to the project scope, schedule, and budget.
b. anecdotal information from the project team members.
c. reports on the amount of money spent because that is the amount of work completed.
d. the names and descriptions of the resources used on the project.
ANSWER: a
FEEDBACK: a.
b.
c.
d.
To control the project, the project team should collect data on the actual performance and
information about any changes to the project scope, schedule, and budget.
To control the project, the project team should collect data on the actual performance and
information about any changes to the project scope, schedule, and budget.
To control the project, the project team should collect data on the actual performance and
information about any changes to the project scope, schedule, and budget.
To control the project, the project team should collect data on the actual performance and
information about any changes to the project scope, schedule, and budget.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.08 – Discuss the project control process
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Analysis
DATE CREATED: 2/18/2017 5:29 PM
DATE MODIFIE
D:
2/18/2017 5:32 PM
132. The actual finish time of an activity
a. is always less than the estimated duration.
b. has a ripple effect in the project and may alter the remaining activities’ earliest start and finish times.
c. has no impact on the critical path of the project.
d. is used to calculate the latest start and finish times of the remaining activities in the project.
ANSWER: b
Copyright Cengage Learning. Powered by Cognero. Page 81Chapter 05
Gido & Clements
FEEDBACK: a.
b.
c.
d.
The actual finish time of an activity has a ripple effect in the project and may alter the
remaining activities’ earliest start and finish times.
The actual finish time of an activity has a ripple effect in the project and may alter the
remaining activities’ earliest start and finish times.
The actual finish time of an activity has a ripple effect in the project and may alter the
remaining activities’ earliest start and finish times.
The actual finish time of an activity has a ripple effect in the project and may alter the
remaining activities’ earliest start and finish times.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
SUPM.GIDO.18.05.08 – Discuss the project control process
NATIONAL STAND
United States – BUSPROG: Analytic
ARDS:
KEYWORDS: Bloom’s: Analysis
DATE CREATED: 2/18/2017 5:32 PM
DATE MODIFIED: 2/18/2017 5:34 PM
133. Schedule updates of the project using actual finish times
a. are calculated forwards and backwards in the project schedule as when planning the project schedule.
b. show how much money has been expended on the project.
c. identify where there are too many resources on the project.
d. show where there are increased risks for the project.
ANSWER: a
FEEDBACK: a.
b.
c.
d.
Schedule updates of the project using actual finish times are calculated forwards and
backwards in the project schedule as when planning the project schedule.
Schedule updates of the project using actual finish times are calculated forwards and
backwards in the project schedule as when planning the project schedule.
Schedule updates of the project using actual finish times are calculated forwards and
backwards in the project schedule as when planning the project schedule.
Schedule updates of the project using actual finish times are calculated forwards and
backwards in the project schedule as when planning the project schedule.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
SUPM.GIDO.18.05.06 – Prepare a project schedule
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Analysis
Copyright Cengage Learning. Powered by Cognero. Page 82Chapter 05
Gido & Clements
DATE CREATED: 2/18/2017 5:34 PM
DATE MODIFIE
D:
2/18/2017 5:36 PM
134. Each time the schedule is recalculated in the project, the schedule should be
a. analyzed to see if it needs further adjustment.
b. accelerated on all paths with a positive slack.
c. examined for a change in critical paths then fast track the new critical path.
d. examined and assign additional resources to the activities with free slack.
ANSWER: a
FEEDBACK: a.
b.
c.
d.
Each time the schedule is recalculated in the project, the schedule should be analyzed
to see if it needs further adjustment.
Each time the schedule is recalculated in the project, the schedule should be analyzed
to see if it needs further adjustment.
Each time the schedule is recalculated in the project, the schedule should be analyzed
to see if it needs further adjustment.
Each time the schedule is recalculated in the project, the schedule should be analyzed
to see if it needs further adjustment.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJEC
TIVES:
SUPM.GIDO.18.05.06 – Prepare a project schedule
NATIONAL STAND
ARDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Analysis
DATE CREATED: 2/18/2017 5:36 PM
DATE MODIFIED: 2/18/2017 5:38 PM
135. If the project needs accelerated, efforts should be concentrated on
a. every activity with long estimated durations.
b. activities on the critical path with short durations to make them shorter.
c. those activities on the path that are near-term or have long estimated durations.
d. all the near term activities in the project.
ANSWER: c
FEEDBACK: a.
b.
c.
d.
If the project needs accelerated, efforts should be concentrated on those activities on the
path that are near-term or have long estimated durations.
If the project needs accelerated, efforts should be concentrated on those activities on the
path that are near-term or have long estimated durations.
If the project needs accelerated, efforts should be concentrated on those activities on the
path that are near-term or have long estimated durations.
If the project needs accelerated, efforts should be concentrated on those activities on the
path that are near-term or have long estimated durations.
POINTS: 1
Copyright Cengage Learning. Powered by Cognero. Page 83Chapter 05
Gido & Clements
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE
Multiple Choice
:
HAS VARIABLES: False
LEARNING OBJE
CTIVES:
NATIONAL STAN
United States – BUSPROG: Analytic
DARDS:
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 5:38 PM
SUPM.GIDO.18.05.09 – Develop updated schedules based on actual progress and changes
DATE MODIFIE
D:
2/18/2017 5:41 PM
136. If the project is ahead of schedule, then concentrated efforts should be made to
a. allow the tasks to start on the days estimated as the earliest start time in the baseline plan.
b. fast track the critical path activities.
c. reduce the number of resources on the project because they are not needed.
d. keep it ahead of schedule.
ANSWER: d
FEEDBACK: a.
b.
c.
d.
If the project is ahead of schedule, then concentrated efforts should be made to keep
it ahead of schedule.
If the project is ahead of schedule, then concentrated efforts should be made to keep
it ahead of schedule.
If the project is ahead of schedule, then concentrated efforts should be made to keep
it ahead of schedule.
If the project is ahead of schedule, then concentrated efforts should be made to keep
it ahead of schedule.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIV
SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
ES:
NATIONAL STANDAR
DS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 5:41 PM
DATE MODIFIED: 2/18/2017 5:44 PM
137. The key to effective project control is
a. assigning a specific resource to gather data from the project team.
b. measuring actual progress and comparing it to planned progress.
c. calculating the costs of the project.
Copyright Cengage Learning. Powered by Cognero. Page 84Chapter 05
Gido & Clements
d. communicating with the project sponsor and the stakeholders for the project.
ANSWER: b
FEEDBACK: a.
b.
c.
d.
The key to effective project control is measuring actual progress and comparing it to
planned progress.
The key to effective project control is measuring actual progress and comparing it to
planned progress.
The key to effective project control is measuring actual progress and comparing it to
planned progress.
The key to effective project control is measuring actual progress and comparing it to
planned progress.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECTIV
ES:
SUPM.GIDO.18.05.08 – Discuss the project control process
NATIONAL STANDAR
DS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Application
DATE CREATED: 2/18/2017 5:44 PM
DATE MODIFIED: 2/18/2017 5:46 PM
138. Schedule control has four steps, they are
a. accelerate tasks on critical path, analyze the schedule, calculate the schedule, identify the next task to fast track.
b. meet with the project team, listen to schedule reports, update the schedule, revise the plan.
c. identify any problems, follow the nine-step problem solving approach, apply the solution, update the schedule.
d. analyze the schedule, decide actions, revise plan, recalculate the schedule.
ANSWER: d
FEEDBACK: a.
b.
c.
d.
Schedule control has four steps, they are analyze the schedule, decide actions, revise
plan, recalculate the schedule.
Schedule control has four steps, they are analyze the schedule, decide actions, revise
plan, recalculate the schedule.
Schedule control has four steps, they are analyze the schedule, decide actions, revise
plan, recalculate the schedule.
Schedule control has four steps, they are analyze the schedule, decide actions, revise
plan, recalculate the schedule.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
LEARNING OBJECT
IVES:
SUPM.GIDO.18.05.10 – Discuss and apply approaches to control the project schedule
NATIONAL STANDA
RDS:
United States – BUSPROG: Analytic
KEYWORDS: Bloom’s: Application
Copyright Cengage Learning. Powered by Cognero. Page 85Chapter 05
Gido & Clements
DATE CREATED: 2/18/2017 5:46 PM
DATE MODIFIED: 2/18/2017 5:48 PM
Copyright Cengage Learning. Powered by Cognero. Page 86
There are no reviews yet.