Successful Project Management 6th Edition By Jack Gido Jim Clements – Test Bank

$15.00

Pay And Download 

Complete Test Bank With Answers

 

 

Sample Questions Posted Below

 

CHAPTER 5: DEVELOPING THE SCHEDULE

1.The estimated resources required for an activity will influence the estimated duration to perform the activity.

a.True

b.False

ANSWER: True

FEEDBACK: Correct The estimated resources required for an activity will influence the estimated duration

to perform the activity.

Incorrect The estimated resources required for an activity will influence the estimated duration

to perform the activity.

2.The estimated activity resources will also be used later for estimating activity costs and determining the project

budget.

a.True

b.False

ANSWER: True

FEEDBACK: Correct The estimated activity resources will also be used later for estimating activity costs and

determining the project budget.

Incorrect The estimated activity resources will also be used later for estimating activity costs and

determining the project budget.

3.It is a good practice to have the person who will be responsible for performing a specific activity estimate the

duration that other resources would need to complete that activity.

a.True

b.False

ANSWER: False

FEEDBACK: Correct It is a good practice to have the person who will be responsible for performing a

specific activity estimate the duration for that activity.

Incorrect It is a good practice to have the person who will be responsible for performing a

specific activity estimate the duration for that activity.

4.For large projects that involve several hundred people performing various activities over several years, it is practical

to have each person estimate activity durations at the beginning of the project.

a.True

b.False

ANSWER: False

FEEDBACK: Correct For large projects that involve several hundred people performing various activities

over several years, it may not be practical to have each person estimate activity

durations at the beginning of the project.

Incorrect For large projects that involve several hundred people performing various activities

over several years, it may not be practical to have each person estimate activity

durations at the beginning of the project.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

5.Each organization or subcontractor responsible for a group or type of activities should always designate an

inexperienced individual to estimate the durations for all the activities for which the organization or subcontractor is

responsible.

a.True

b.False

ANSWER: False

FEEDBACK: Correct Each organization or subcontractor responsible for a group or type of activities may

designate an experienced individual to estimate the durations for all the activities for

which the organization or subcontractor is responsible.

Incorrect Each organization or subcontractor responsible for a group or type of activities may

designate an experienced individual to estimate the durations for all the activities for

which the organization or subcontractor is responsible.

6.The estimated duration for an activity must be based on the estimated quantity of resources required to perform the

activity.

a.True

b.False

ANSWER: True

FEEDBACK: Correct The estimated duration for an activity must be based on the estimated quantity of

resources required to perform the activity.

Incorrect The estimated duration for an activity must be based on the estimated quantity of

resources required to perform the activity.

7.The estimated duration should be aggressive, yet unrealistic.

a.True

b.False

ANSWER: False

FEEDBACK: Correct The estimated duration should be aggressive, yet realistic.

Incorrect The estimated duration should be aggressive, yet realistic.

8.Playing the game of inflating estimated durations in anticipation of the project manager negotiating shorter durations

is a good practice.

a.True

b.False

ANSWER: False

FEEDBACK: Correct Playing the game of inflating estimated durations in anticipation of the project

manager negotiating shorter durations is not a good practice.

Incorrect Playing the game of inflating estimated durations in anticipation of the project

manager negotiating shorter durations is not a good practice.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

9.Padding estimates with the vision of becoming a hero when the activities are completed in less time than estimated is

not a good practice.

a.True

b.False

ANSWER: True

FEEDBACK: Correct Padding estimates with the vision of becoming a hero when the activities are

completed in less time than estimated is not a good practice.

Incorrect Padding estimates with the vision of becoming a hero when the activities are

completed in less time than estimated is not a good practice.

10.At the beginning of every project, it is possible to estimate the durations for all activities with a high level of

confidence regarding their accuracy.

a.True

b.False

ANSWER: False

FEEDBACK: Correct At the beginning of the project, it may not be possible to estimate the durations for all

activities with a level of confidence regarding their accuracy.

Incorrect At the beginning of the project, it may not be possible to estimate the durations for all

activities with a level of confidence regarding their accuracy.

11.The project team can progressively elaborate the estimated durations as more information is known or becomes

clear to allow for more accurate estimated durations.

a.True

b.False

ANSWER: True

FEEDBACK: Correct The project team can progressively elaborate the estimated durations as more

information is known or becomes clear to allow for more accurate estimated durations.

Incorrect The project team can progressively elaborate the estimated durations as more

information is known or becomes clear to allow for more accurate estimated durations.

12.A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in

a network diagram.

a.True

b.False

ANSWER: True

FEEDBACK: Correct A consistent time base, such as hours or days or weeks, should be used for all

the estimated durations of activities in a network diagram.

Incorrect A consistent time base, such as hours or days or weeks, should be used for all

the estimated durations of activities in a network diagram.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

13.The sponsor or customer often states the project required completion time in the project charter, RFP, or contract.

a.True

b.False

ANSWER: True

FEEDBACK: Correct The sponsor or customer often states the project required completion time in the

project charter, RFP, or contract.

Incorrect The sponsor or customer often states the project required completion time in the

project charter, RFP, or contract.

14.The contractor may not want to commit to completing the project by a specific date until the customer has approved

the contract.

a.True

b.False

ANSWER: True

FEEDBACK: Correct The contractor may not want to commit to completing the project by a specific

date until the customer has approved the contract.

Incorrect The contractor may not want to commit to completing the project by a specific

date until the customer has approved the contract.

15.The latest finish time for a specific activity must be the same as or earlier than the earliest of all the latest start times

of all the activities emerging directly from that specific activity.

a.True

b.False

ANSWER: True

FEEDBACK: Correct The latest finish time for a specific activity must be the same as or earlier than the

earliest of all the latest start times of all the activities emerging directly from that

specific activity.

Incorrect The latest finish time for a specific activity must be the same as or earlier than the

earliest of all the latest start times of all the activities emerging directly from that

specific activity.

16.If the total slack is zero, the activities on the path do not need to be accelerated but cannot be delayed.

a.True

b.False

ANSWER: True

FEEDBACK: Correct If the total slack is zero, the activities on the path do not need to be accelerated

but cannot be delayed.

Incorrect If the total slack is zero, the activities on the path do not need to be accelerated

but cannot be delayed.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

17.A Gantt chart is the often the name for the network diagram tool for planning and scheduling.

a.True

b.False

ANSWER: False

FEEDBACK: Correct A Gantt chart is the often the name for the bar chart tool for planning and scheduling.

Incorrect A Gantt chart is the often the name for the bar chart tool for planning and scheduling.

18.This longest path in the overall network diagram is called the network path.

a.True

b.False

ANSWER: False

FEEDBACK: Correct This longest path in the overall network diagram is called the critical path.

Incorrect This longest path in the overall network diagram is called the critical path.

19.One way to determine which activities make up the critical path is to find which ones have the least slack.

a.True

b.False

ANSWER: True

FEEDBACK: Correct One way to determine which activities make up the critical path is to find which ones

have the least slack.

Incorrect One way to determine which activities make up the critical path is to find which ones

have the least slack.

20.The project control process starts with establishing a baseline plan that shows how the project scope will be

accomplished on schedule and over budget.

a.True

b.False

ANSWER: False

FEEDBACK: Correct The project control process starts with establishing a baseline plan that shows how

the project scope will be accomplished on schedule and within budget.

Incorrect The project control process starts with establishing a baseline plan that shows how

the project scope will be accomplished on schedule and within budget.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

21.Once this baseline plan is agreed upon by the customer and the contractor or project team, the project work can be

performed.

a.True

b.False

ANSWER: True

FEEDBACK: Correct Once this baseline plan is agreed upon by the customer and the contractor or

project team, the project work can be performed.

Incorrect Once this baseline plan is agreed upon by the customer and the contractor or

project team, the project work can be performed.

22.It is necessary to monitor the progress to ensure that everything is going according to the plan.

a.True

b.False

ANSWER: True

FEEDBACK: Correct It is necessary to monitor the progress to ensure that everything is going according to

the plan.

Incorrect It is necessary to monitor the progress to ensure that everything is going according to

the plan.

23.Project management is a proactive approach to controlling a project to ensure that the project objective is

accomplished, even when things do not go according to plan.

a.True

b.False

ANSWER: True

FEEDBACK: Correct Project management is a proactive approach to controlling a project to ensure

that the project objective is accomplished, even when things do not go according

to plan.

Incorrect Project management is a proactive approach to controlling a project to ensure that

the project objective is accomplished, even when things do not go according to

plan.

24.Throughout a project, changes may occur that have an impact on the schedule.

a.True

b.False

ANSWER: True

FEEDBACK: Correct Throughout a project, changes may occur that have an impact on the schedule.

Incorrect Throughout a project, changes may occur that have an impact on the schedule.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

25.Changes might be initiated by the customer or the project team, or they might be the result of an unanticipated

occurrence.

a.True

b.False

ANSWER: True

FEEDBACK: Correct Changes might be initiated by the customer or the project team, or they might be

the result of an unanticipated occurrence.

Incorrect Changes might be initiated by the customer or the project team, or they might be

the result of an unanticipated occurrence.

26.Changes requested early in the project always have less impact on schedule and budget than if they are requested

later in the project.

a.True

b.False

ANSWER: False

FEEDBACK: Correct Changes requested early in the project may have less impact on schedule and budget

than if they are requested later in the project.

Incorrect Changes requested early in the project may have less impact on schedule and budget

than if they are requested later in the project.

27.When the customer requests a change, the contractor or project team should estimate the impact on the project

schedule and budget and then go ahead with the work without customer approval.

a.True

b.False

ANSWER: False

FEEDBACK: Correct When the customer requests a change, the contractor or project team should estimate

the impact on the project schedule and budget and then obtain customer approval

before proceeding. If the customer approves the proposed revisions to the project

schedule and budget, then any additional activities, revised estimated durations, and

revised estimated resources and associated costs should be incorporated into the

project schedule and budget.

Incorrect When the customer requests a change, the contractor or project team should estimate

the impact on the project schedule and budget and then obtain customer approval

before proceeding. If the customer approves the proposed revisions to the project

schedule and budget, then any additional activities, revised estimated durations, and

revised estimated resources and associated costs should be incorporated into the

project schedule and budget.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

28.An updated project schedule can be generated regularly that forecasts whether the project will finish ahead of or

behind its required completion time.

a.True

b.False

ANSWER: True

FEEDBACK: Correct An updated project schedule can be generated regularly that forecasts whether the

project will finish ahead of or behind its required completion time.

Incorrect An updated project schedule can be generated regularly that forecasts whether the

project will finish ahead of or behind its required completion time.

29.The amount of slack should determine the priority with which these concentrated efforts are applied.

a.True

b.False

ANSWER: True

FEEDBACK: Correct The amount of slack should determine the priority with which these concentrated efforts

are applied.

Incorrect The amount of slack should determine the priority with which these concentrated efforts

are applied.

30.A change in the estimated duration of any activity on that path will cause a corresponding change in the slack for

that path.

a.True

b.False

ANSWER: True

FEEDBACK: Correct A change in the estimated duration of any activity on that path will cause a

corresponding change in the slack for that path.

Incorrect A change in the estimated duration of any activity on that path will cause a

corresponding change in the slack for that path.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

31.When estimating resources for activities to estimate the activity’s duration, the

a.availability of each resource has to be taken into account.

b.name of each resource has to be taken into account.

c.cost of each resource has to be taken into account.

d.security clearance of each resource has to be taken into account.

ANSWER: a

FEEDBACK: a. When estimating resources for activities, the availability of each resource has to be taken into

account.

b.When estimating resources for activities, the availability of each resource has to be taken into

account.

c.When estimating resources for activities, the availability of each resource has to be taken into

account.

d.When estimating resources for activities, the availability of each resource has to be taken into

account.

32.It is important to know what types of resources are available, in what quantities, and during what time periods to

determine

a.that the project team will be larger than necessary to complete the project.

b.how to enter resources into a project management information system.

c.if the right types of resources will be available in sufficient quantities during the time periods that the project

requires.

d.that the project will be less expensive than estimated.

ANSWER: c

FEEDBACK: a. It is important to know what types of resources are available, in what quantities, and during

what time periods to determine if the right types of resources will be available in sufficient

quantities during the time periods that the project requires.

b.It is important to know what types of resources are available, in what quantities, and during

what time periods to determine if the right types of resources will be available in sufficient

quantities during the time periods that the project requires.

c.It is important to know what types of resources are available, in what quantities, and during

what time periods to determine if the right types of resources will be available in sufficient

quantities during the time periods that the project requires.

d.It is important to know what types of resources are available, in what quantities, and during

what time periods to determine if the right types of resources will be available in sufficient

quantities during the time periods that the project requires.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

33.When considering the availability of resources, it may be necessary to make some assumptions, such as

a.the unemployment rate in the community.

b.the ability to hire additional individuals with the appropriate expertise in time for when they will be required to

work on a project.

c.the number of project deliverables.

d.the type of organizational structure of the sponsor.

ANSWER: b

FEEDBACK: a. When considering the availability of resources, it may be necessary to make some

assumptions, such as the ability to hire additional individuals with the appropriate expertise in

time for when they will be required to work on a project.

b.When considering the availability of resources, it may be necessary to make some assumptions,

such as the ability to hire additional individuals with the appropriate expertise in time for when

they will be required to work on a project.

c.When considering the availability of resources, it may be necessary to make some assumptions,

such as the ability to hire additional individuals with the appropriate expertise in time for when

they will be required to work on a project.

d.When considering the availability of resources, it may be necessary to make some assumptions,

such as the ability to hire additional individuals with the appropriate expertise in time for when

they will be required to work on a project.

34.In many cases, especially for smaller projects, most activities involve people resources—that is,

a.all the people who are employed by the project sponsor.

b.all the people who are employed by the project contractor.

c.the members of the project team who may be utilized full time or part time during the project.

d.the stakeholders for the project.

ANSWER: c

FEEDBACK: a. In many cases, especially for smaller projects, most activities involve people resources—that

the members of the project team who may be utilized full time or part time during the

is, project.

b.In many cases, especially for smaller projects, most activities involve people resources—that is,

the members of the project team who may be utilized full time or part time during the project.

c.In many cases, especially for smaller projects, most activities involve people resources—that is,

the members of the project team who may be utilized full time or part time during the project.

d.In many cases, especially for smaller projects, most activities involve people resources—that is,

the members of the project team who may be utilized full time or part time during the project.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

35.The estimated types and quantities of resources required for an activity together with the availability of those

resources will influence the

a.estimated duration for how long it will take to perform the activity.

b.project scope document description.

c.project’s acceptance criteria.

d.actual costs of work performed.

ANSWER: a

FEEDBACK: a. The estimated types and quantities of resources required for an activity together with the

availability of those resources will influence the estimated duration for how long it will take to

perform the activity.

b.The estimated types and quantities of resources required for an activity together with the

availability of those resources will influence the estimated duration for how long it will take to

perform the activity.

c.The estimated types and quantities of resources required for an activity together with the

availability of those resources will influence the estimated duration for how long it will take to

perform the activity.

d.The estimated types and quantities of resources required for an activity together with the

availability of those resources will influence the estimated duration for how long it will take to

perform the activity.

36.When estimating the types and quantities of resources required for each specific activity, it is valuable to involve a

person who

a.is hired by the customer to be a consultant regardless of experience on the type of project.

b.has expertise or experience with the activity to help make the estimate.

c.has experience negotiating contracts.

d.has the most experience using a project management information system.

ANSWER: b

FEEDBACK: a. When estimating the types and quantities of resources required for each specific activity, it is

valuable to involve a person who has expertise or experience with the activity to help make the

estimate.

b.When estimating the types and quantities of resources required for each specific activity, it is

valuable to involve a person who has expertise or experience with the activity to help make the

estimate.

c.When estimating the types and quantities of resources required for each specific activity, it is

valuable to involve a person who has expertise or experience with the activity to help make the

estimate.

d.When estimating the types and quantities of resources required for each specific activity, it is

valuable to involve a person who has expertise or experience with the activity to help make the

estimate.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

37.The estimated duration for each activity must be the total elapsed time,

a.the time for the work to be done plus any associated waiting time.

b.the time for the task plus the planning time for the project.

c.the time required for the work times the number of resources assigned to the project.

d.the time for the task plus the time to review and accept the deliverable.

ANSWER: a

FEEDBACK: a. The estimated duration for each activity must be the total elapsed time, the time for the work to

be done plus any associated waiting time.

b.The estimated duration for each activity must be the total elapsed time, the time for the work to

be done plus any associated waiting time.

c.The estimated duration for each activity must be the total elapsed time, the time for the work to

be done plus any associated waiting time.

d.The estimated duration for each activity must be the total elapsed time, the time for the work to

be done plus any associated waiting time.

38.Having the person who will be responsible for performing a specific activity estimate the duration for that activity

from that person and that may be introduced by having one person estimate the durations for all of the

activities.

a.takes more effort, creates a problem

b.gives the status of the project, sets best practices

c.generates a commitment , avoids any bias

d.elevates the placement perception, creates errors

ANSWER: c

FEEDBACK: a. Having the person who will be responsible for performing a specific activity estimate the

duration for that activity generates a commitment from that person and avoids any bias that

may be introduced by having one person estimate the durations for all of the activities.

b.Having the person who will be responsible for performing a specific activity estimate the

duration for that activity generates a commitment from that person and avoids any bias that

may be introduced by having one person estimate the durations for all of the activities.

c.Having the person who will be responsible for performing a specific activity estimate the

duration for that activity generates a commitment from that person and avoids any bias that

may be introduced by having one person estimate the durations for all of the activities.

d.Having the person who will be responsible for performing a specific activity estimate the

duration for that activity generates a commitment from that person and avoids any bias that

may be introduced by having one person estimate the durations for all of the activities.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

39.If an organization or subcontractor has performed similar projects in the past and has kept records of how long

specific activities actually took, these historical data

a.can be used as a guide in estimating the durations of similar activities for future projects.

b.have no value for the current project.

c.should be stored in files.

d.should be shared with the customer after the contract is signed to show that the contractor can complete the

project.

ANSWER: a

FEEDBACK: a. If an organization or subcontractor has performed similar projects in the past and has kept

records of how long specific activities actually took, these historical data can be used as a

guide in estimating the durations of similar activities for future projects.

b.If an organization or subcontractor has performed similar projects in the past and has kept

records of how long specific activities actually took, these historical data can be used as a guide

in estimating the durations of similar activities for future projects.

c.If an organization or subcontractor has performed similar projects in the past and has kept

records of how long specific activities actually took, these historical data can be used as a guide

in estimating the durations of similar activities for future projects.

d.If an organization or subcontractor has performed similar projects in the past and has kept

records of how long specific activities actually took, these historical data can be used as a guide

in estimating the durations of similar activities for future projects.

40.People sometimes perform to expectations, their effort will expand to fill the whole number of scheduled days

allotted,

a.even if the number of resources assigned to the task is reduced.

b.even if the activity could have been performed in a shorter time.

c.even if part of the time for the task is waiting time.

d.even if the activity could have been performed in a longer time.

ANSWER: b

FEEDBACK: a. People sometimes perform to expectations, their effort will expand to fill the whole number of

scheduled days allotted, even if the activity could have been performed in a shorter time.

b.People sometimes perform to expectations, their effort will expand to fill the whole number of

scheduled days allotted, even if the activity could have been performed in a shorter time.

c.People sometimes perform to expectations, their effort will expand to fill the whole number of

scheduled days allotted, even if the activity could have been performed in a shorter time.

d.People sometimes perform to expectations, their effort will expand to fill the whole number of

scheduled days allotted, even if the activity could have been performed in a shorter time.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

41.Throughout the performance of the project, some activities will take longer than their estimated duration, others will

be done in less time than their estimated duration, and

a.many will take no time to complete.

b.many will not be completed.

c.others are to be done by two project teams.

d.a few may conform to the estimated duration exactly.

ANSWER: d

FEEDBACK: a. Throughout the performance of the project, some activities will take longer than their estimated

duration, others will be done in less time than their estimated duration, and a few may conform

to the estimated duration exactly.

b.Throughout the performance of the project, some activities will take longer than their estimated

duration, others will be done in less time than their estimated duration, and a few may conform

to the estimated duration exactly.

c.Throughout the performance of the project, some activities will take longer than their estimated

duration, others will be done in less time than their estimated duration, and a few may conform

to the estimated duration exactly.

d.Throughout the performance of the project, some activities will take longer than their estimated

duration, others will be done in less time than their estimated duration, and a few may conform

to the estimated duration exactly.

42.With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible

to use three time estimates:

a.an original estimate, a petrified estimate, and a most likely estimate.

b.an optimistic estimate, a pessimistic estimate, and a most likely estimate.

c.an optimized estimate, a primary estimate, and a most likely estimate.

d.an opportunity estimate, a pragmatic estimate, and a most likely estimate.

ANSWER: b

FEEDBACK: a. With projects for which there is a high degree of uncertainty about the estimated durations for

activities, it is possible to use three time estimates: an optimistic estimate, a pessimistic estimate,

and a most likely estimate.

b.With projects for which there is a high degree of uncertainty about the estimated durations for

activities, it is possible to use three time estimates: an optimistic estimate, a pessimistic estimate,

and a most likely estimate.

c.With projects for which there is a high degree of uncertainty about the estimated durations for

activities, it is possible to use three time estimates: an optimistic estimate, a pessimistic estimate,

and a most likely estimate.

d.With projects for which there is a high degree of uncertainty about the estimated durations for

activities, it is possible to use three time estimates: an optimistic estimate, a pessimistic estimate,

and a most likely estimate.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

43.In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is

necessary to

a.say who has responsibility for the first task.

b.enter the tasks into a project management information system.

c.select an estimated start time and a required completion time for the overall project.

d.edit the calendars for the resources in the project management information system.

ANSWER: c

FEEDBACK: a. In order to establish a basis from which to calculate a schedule using the estimated durations

for the activities, it is necessary to select an estimated start time and a required completion time

for the overall project.

b.In order to establish a basis from which to calculate a schedule using the estimated durations

for the activities, it is necessary to select an estimated start time and a required completion time

for the overall project.

c.In order to establish a basis from which to calculate a schedule using the estimated durations

for the activities, it is necessary to select an estimated start time and a required completion time

for the overall project.

d.In order to establish a basis from which to calculate a schedule using the estimated durations

for the activities, it is necessary to select an estimated start time and a required completion time

for the overall project.

44.Earliest start time (ES) is the earliest time at which a specific activity can begin

a.calculated on the basis of the project estimated start time and the estimated durations of preceding activities.

b.calculated on the basis of the project estimated finish time and the estimated durations of preceding activities.

c.calculated on the basis of the project estimated start time and the estimated durations of succeeding activities.

d.calculated on the basis of the project estimated start time and the estimated durations of approaching

activities.

ANSWER: a

FEEDBACK: a. Earliest start time (ES) is the earliest time at which a specific activity can begin, calculated on

the basis of the project estimated start time and the estimated durations of preceding activities.

b.Earliest start time (ES) is the earliest time at which a specific activity can begin, calculated on

the basis of the project estimated start time and the estimated durations of preceding activities.

c.Earliest start time (ES) is the earliest time at which a specific activity can begin, calculated on

the basis of the project estimated start time and the estimated durations of preceding activities.

d.Earliest start time (ES) is the earliest time at which a specific activity can begin, calculated on

the basis of the project estimated start time and the estimated durations of preceding activities.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

45.Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated

a.by subtracting the activity’s estimated duration from the earliest finish time of the activity’s predecessor: EF =

EF predecessor – Estimated Duration.

b.by subtracting the activity’s estimated duration to the activity’s earliest start time: EF = ES • Estimated

Duration.

c.by adding the activity’s estimated duration to the earliest start time of the activity’s succeeding activity: EF =

ES succeeding activity + Estimated Duration.

d.by adding the activity’s estimated duration to the activity’s earliest start time: EF = ES + Estimated Duration.

ANSWER: d

FEEDBACK: a. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

b.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

c.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

d.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

46.The ES and EF times are determined by calculating forward, that is, by

a.adding all the times together for the project.

b.working through the network diagram from the beginning of the project to the end of the project.

c.calculating the optimistic and pessimistic times for the project.

d.working through the network diagram from the end of the project to the beginning of the project.

ANSWER: b

FEEDBACK: a. The ES and EF times are determined by calculating forward, that is, by working through the

network diagram from the beginning of the project to the end of the project.

b.The ES and EF times are determined by calculating forward, that is, by working through the

network diagram from the beginning of the project to the end of the project.

c.The ES and EF times are determined by calculating forward, that is, by working through the

network diagram from the beginning of the project to the end of the project.

d.The ES and EF times are determined by calculating forward, that is, by working through the

network diagram from the beginning of the project to the end of the project.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

47.The earliest start time for a specific activity must be leading directly into that specific activity.

a.earlier than

b.the same as

c.the same as or later than

d.later than

the latest of all the earliest finish times of all the activities

ANSWER: c

FEEDBACK: a. The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

b.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

c.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

d.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

48.Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2

days.

a.day 5

b.day 3

c.day 1

d.Cannot be calculated based upon information given.

ANSWER: a

FEEDBACK: a. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

b.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

c.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

d.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

49.Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2

days.

a.day 5

b.day 3

c.day 1

d.Cannot be calculated based upon information given.

ANSWER: b

FEEDBACK: a. The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

b.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

c.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

d.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

50.Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor,

Task C, finishes on day 4, and the duration of Task D is 2 days.

a.day 6

b.day 3

c.day 4

d.Cannot be calculated based upon information given.

ANSWER: c

FEEDBACK: a. The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

b.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

c.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

d.The earliest start time for a specific activity must be the same as or later than the latest of all

the earliest finish times of all the activities leading directly into that specific activity.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

51.Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor,

Task C, finishes on day 4, and the duration of Task D is 2 days.

a.day 6

b.day 3

c.day 4

d.Cannot be calculated based upon information given.

ANSWER: a

FEEDBACK: a. Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

b.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

c.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

d.Earliest finish time (EF) is the earliest time by which a specific activity can be completed,

calculated by adding the activity’s estimated duration to the activity’s earliest start time: EF =

ES + Estimated Duration.

52.Latest finish time (LF) is the latest time by which a specific activity must be

a.started in order for the entire project to be finished by its required completion time.

b.completed in order for the entire project to be finished by its required completion time.

c.started in order for the entire project to be started by its required completion time.

d.completed in order for the entire project to be started by its required completion time.

ANSWER: b

FEEDBACK: a. Latest finish time (LF) is the latest time by which a specific activity must be completed in

order for the entire project to be finished by its required completion time.

b.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

c.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

d.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

53.Latest start time (LS) is the latest time by which a specific activity must be

a.started in order for the entire project to be finished by its required completion time.

b.started in order for the entire project to be started by its required completion time.

c.finished in order for the entire project to be finished by its required completion time.

d.finished in order for the entire project to be started by its required completion time.

ANSWER: a

FEEDBACK: a. Latest start time (LS) is the latest time by which a specific activity must be started in order for

the entire project to be finished by its required completion time.

b.Latest start time (LS) is the latest time by which a specific activity must be started in order for

the entire project to be finished by its required completion time.

c.Latest start time (LS) is the latest time by which a specific activity must be started in order for

the entire project to be finished by its required completion time.

d.Latest start time (LS) is the latest time by which a specific activity must be started in order for

the entire project to be finished by its required completion time.

54.Latest start time is calculated by

a.subtracting the activity’s estimated duration from the activity’s succeeding activity’s latest finish time: LS = LF

succeeding activity – Estimated Duration.

b.adding the activity’s estimated duration to the predecessor of the activity’s latest start time: LS = LS

predecessor + Estimated Duration.

c.subtracting the activity’s estimated duration from the activity’s latest finish time: LS = LF – Estimated

Duration.

d.adding the activity’s estimated duration to the activity’s latest finish time: LS = LF + Estimated Duration.

ANSWER: c

FEEDBACK: a. Latest start time is calculated by subtracting the activity’s estimated duration from the

activity’s latest finish time: LS = LF – Estimated Duration.

b.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

c.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

d.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

55.Calculate the latest finish for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E,

has a latest start of day 7, and the duration of Task B is 2 days.

a.day 5

b.day 3

c.day 7

d.Cannot be calculated based upon information given.

ANSWER: c

FEEDBACK: a. Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

b.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

c.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

d.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

56.Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has

a latest start of day 7, and the duration of Task B is 2 days.

a.day 5

b.day 3

c.day 7

d.Cannot be calculated based upon information given.

ANSWER: a

FEEDBACK: a. Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

b.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

c.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

d.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

57.Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor,

Task E, has a latest start on day 10, and the duration of Task D is 2 days.

a.day 8

b.day 7

c.day 12

d.Cannot be calculated based upon information given.

ANSWER: b

FEEDBACK: a. Latest start time is calculated by subtracting the activity’s estimated duration from the

activity’s latest finish time: LS = LF – Estimated Duration.

b.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

c.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

d.Latest start time is calculated by subtracting the activity’s estimated duration from the activity’s

latest finish time: LS = LF – Estimated Duration.

58.Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor,

Task E, has a latest start on day 10, and the duration of Task D is 2 days.

a.day 9

b.day 10

c.day 12

d.Cannot be calculated based upon information given.

ANSWER: a

FEEDBACK: a. Latest finish time (LF) is the latest time by which a specific activity must be completed in

order for the entire project to be finished by its required completion time.

b.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

c.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

d.Latest finish time (LF) is the latest time by which a specific activity must be completed in order

for the entire project to be finished by its required completion time.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

59.Total slack for the project is the difference between

a.LF time of last activity and the project required completion time.

b.EF time of last activity and the project required completion time.

c.ES time of last activity and the project required completion time.

d.LS time of last activity and the project required completion time.

ANSWER: b

FEEDBACK: a. Total slack for the project is the difference between EF time of last activity and the project

required completion time.

b.Total slack for the project is the difference between EF time of last activity and the project

required completion time.

c.Total slack for the project is the difference between EF time of last activity and the project

required completion time.

d.Total slack for the project is the difference between EF time of last activity and the project

required completion time.

60.Total Slack is sometimes called

a.drift.

b.ride.

c.float.

d.sink.

ANSWER: c

FEEDBACK: a. Total Slack is sometimes called float.

b.Total Slack is sometimes called float.

c.Total Slack is sometimes called float.

d.Total Slack is sometimes called float.

61.Total slack is calculated for each of the activities by finding the difference between

a.the ES of the activity and the LF of the activity or the difference between the EF and LS of the activity.

b.the EF of the activity and the LS of the activity or the difference between the ES and LF of the activity.

c.the EF of the activity and the LF of the activity or the difference between the ES and LS of the activity.

d.the ES of the activity and the LF of the activity or the difference between the ES and LF of the activity.

ANSWER: c

FEEDBACK: a. Total slack is calculated for each of the activities by finding the difference between the EF of

the activity and the LF of the activity or the difference between the ES and LS of the activity.

b.Total slack is calculated for each of the activities by finding the difference between the EF of

the activity and the LF of the activity or the difference between the ES and LS of the activity.

c.Total slack is calculated for each of the activities by finding the difference between the EF of

the activity and the LF of the activity or the difference between the ES and LS of the activity.

d.Total slack is calculated for each of the activities by finding the difference between the EF of

the activity and the LF of the activity or the difference between the ES and LS of the activity.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

62.Negative slack indicates a lack of slack over the entire project and the amount of time

a.an activity must be accelerated to complete the project by the required completion time.

b.an activity must be delayed to complete the project by the required completion time.

c.each activity on the critical must be accelerated to complete the project by the required completion time.

d.all activities in the project must be accelerated to complete the project by the required completion time.

ANSWER: a

FEEDBACK: a. Negative slack indicates a lack of slack over the entire project and the amount of time an

activity must be accelerated to complete the project by the required completion time.

b.Negative slack indicates a lack of slack over the entire project and the amount of time an

activity must be accelerated to complete the project by the required completion time.

c.Negative slack indicates a lack of slack over the entire project and the amount of time an

activity must be accelerated to complete the project by the required completion time.

d.Negative slack indicates a lack of slack over the entire project and the amount of time an

activity must be accelerated to complete the project by the required completion time.

63.Positive slack indicates the maximum amount of time

a.that the activities on the critical path should be accelerated to complete the project by the required completion

time.

b.that each of the activities in the project can be delayed without jeopardizing completion of the project by the

required completion time.

c.that the activities with the positive slack should be accelerated to complete the project by the required

completion time.

d.that the activities on a particular path can be delayed without jeopardizing completion of the project by the

required completion time.

ANSWER: d

FEEDBACK: a. Positive slack indicates the maximum amount of time that the activities on a particular path can

be delayed without jeopardizing completion of the project by the required completion time.

b.Positive slack indicates the maximum amount of time that the activities on a particular path can

be delayed without jeopardizing completion of the project by the required completion time.

c.Positive slack indicates the maximum amount of time that the activities on a particular path can

be delayed without jeopardizing completion of the project by the required completion time.

d.Positive slack indicates the maximum amount of time that the activities on a particular path can

be delayed without jeopardizing completion of the project by the required completion time.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

64.Free slack is the amount of time a specific activity can be

a.postponed without delaying the earliest start time of its immediately preceding activities.

b.postponed without delaying the earliest start time of its immediately succeeding activities.

c.accelerated without delaying the latest start time of its immediately succeeding activities.

d.accelerated without delaying the latest finish time of its immediately preceding activities.

ANSWER: b

FEEDBACK: a. Free slack is the amount of time a specific activity can be postponed without delaying the

earliest start time of its immediately succeeding activities.

b.Free slack is the amount of time a specific activity can be postponed without delaying the

earliest start time of its immediately succeeding activities.

c.Free slack is the amount of time a specific activity can be postponed without delaying the

earliest start time of its immediately succeeding activities.

d.Free slack is the amount of time a specific activity can be postponed without delaying the

earliest start time of its immediately succeeding activities.

65.Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific

activity and then

a.adding it from the values of total slack for the other activities also entering into that same activity.

b.subtracting it from the values of total slack for the other activities succeeding after that same activity.

c.subtracting it from the values of total slack for the other activities also entering into that same activity.

d.adding it from the values of total slack for the other activities succeeding after that same activity.

ANSWER: c

FEEDBACK: a. Free slack is calculated by finding the lowest of the values of total slack for all the activities

entering into a specific activity and then subtracting it from the values of total slack for the

other activities also entering into that same activity.

b.Free slack is calculated by finding the lowest of the values of total slack for all the activities

entering into a specific activity and then subtracting it from the values of total slack for the

other activities also entering into that same activity.

c.Free slack is calculated by finding the lowest of the values of total slack for all the activities

entering into a specific activity and then subtracting it from the values of total slack for the

other activities also entering into that same activity.

d.Free slack is calculated by finding the lowest of the values of total slack for all the activities

entering into a specific activity and then subtracting it from the values of total slack for the

other activities also entering into that same activity.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

66.The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days.

Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have?

a.Negative 5 days slack.

b.Positive 5 days slack.

c.Positive 17 days slack.

d.Positive 3 days slack.

ANSWER: b

FEEDBACK: a. The total completion time is 25 days. The tasks are planned to take 20 days (7+5+8). The

project has 5 days of slack.

b.The total completion time is 25 days. The tasks are planned to take 20 days (7+5+8). The

project has 5 days of slack.

c.The total completion time is 25 days. The tasks are planned to take 20 days (7+5+8). The

project has 5 days of slack.

d.The total completion time is 25 days. The tasks are planned to take 20 days (7+5+8). The

project has 5 days of slack.

67.The estimated duration for each activity is indicated by a bar spanning the period

a.during which the activity is expected to be accomplished.

b.of the part of the activity that has more than one work resource assigned.

c.during which the activity has waiting time for the activity to be accomplished.

d.during which the project is expected to be accomplished.

ANSWER: a

FEEDBACK: a. The estimated duration for each activity is indicated by a bar spanning the period during which

the activity is expected to be accomplished.

b.The estimated duration for each activity is indicated by a bar spanning the period during which

the activity is expected to be accomplished.

c.The estimated duration for each activity is indicated by a bar spanning the period during which

the activity is expected to be accomplished.

d.The estimated duration for each activity is indicated by a bar spanning the period during which

the activity is expected to be accomplished.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

68.As the project progresses, the actual finish times (AFs) of completed activities will determine

a.the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the

total slack.

b.the earliest start and earliest finish times for the completed activities in the network diagram, as well as the

total slack.

c.the latest start and latest finish times for the remaining activities in the network diagram, as well as the total

slack.

d.the latest start and latest finish times for the completed activities in the network diagram, as well as the total

slack.

ANSWER: a

FEEDBACK: a. As the project progresses, the actual finish times (AFs) of completed activities will determine

the earliest start and earliest finish times for the remaining activities in the network diagram, as

well as the total slack.

b.As the project progresses, the actual finish times (AFs) of completed activities will determine

the earliest start and earliest finish times for the remaining activities in the network diagram, as

well as the total slack.

c.As the project progresses, the actual finish times (AFs) of completed activities will determine

the earliest start and earliest finish times for the remaining activities in the network diagram, as

well as the total slack.

d.As the project progresses, the actual finish times (AFs) of completed activities will determine

the earliest start and earliest finish times for the remaining activities in the network diagram, as

well as the total slack.

69.The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days.

Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed

instead of seven days. How much slack does the project have now that Task A is finished?

a.Negative 5 days slack.

b.Positive 5 days slack.

c.Positive 16 days slack.

d.Positive 3 days slack.

ANSWER: d

FEEDBACK: a. The total completion time is 25 days. The tasks were planned to take 20 days (7+5+8). Task

A’s actual finish time is 9 days. The expected time of the project is now 22 days (9+5+8).

The project has 3 days of slack.

b.The total completion time is 25 days. The tasks were planned to take 20 days (7+5+8). Task

A’s actual finish time is 9 days. The expected time of the project is now 22 days (9+5+8). The

project has 3 days of slack.

c.The total completion time is 25 days. The tasks were planned to take 20 days (7+5+8). Task

A’s actual finish time is 9 days. The expected time of the project is now 22 days (9+5+8). The

project has 3 days of slack.

d.The total completion time is 25 days. The tasks were planned to take 20 days (7+5+8). Task

A’s actual finish time is 9 days. The expected time of the project is now 22 days (9+5+8). The

project has 3 days of slack.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

70.The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days.

Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed

instead of seven days. What are the ES and EF times for Task B now that Task A is complete?

a.ES = 9, EF = 14

b.ES = 7, EF = 12

c.ES = 5, EF = 14

d.ES = 5, EF = 12

ANSWER: a

FEEDBACK: a. The finish time for Task A is nine days. The ES for Task B is the same as the finish time for

Task A. The EF for Task B is the ES of Task B + Estimated Duration of Task B = 9+5 = 14

days.

b.The finish time for Task A is nine days. The ES for Task B is the same as the finish time for

Task A. The EF for Task B is the ES of Task B + Estimated Duration of Task B = 9+5 = 14

days.

c.The finish time for Task A is nine days. The ES for Task B is the same as the finish time for

Task A. The EF for Task B is the ES of Task B + Estimated Duration of Task B = 9+5 = 14

days.

d.The finish time for Task A is nine days. The ES for Task B is the same as the finish time for

Task A. The EF for Task B is the ES of Task B + Estimated Duration of Task B = 9+5 = 14

days.

71.The project control process involves all of the following except

a.regularly gathering data on project performance.

b.comparing actual performance to planned performance.

c.taking corrective action immediately if actual performance is behind planned performance.

d.having social gatherings with the project team.

ANSWER: d

FEEDBACK: a. The project control process involves regularly gathering data on project performance,

comparing actual performance to planned performance, and taking corrective action

immediately if actual performance is behind planned performance.

b.The project control process involves regularly gathering data on project performance,

comparing actual performance to planned performance, and taking corrective action

immediately if actual performance is behind planned performance.

c.The project control process involves regularly gathering data on project performance,

comparing actual performance to planned performance, and taking corrective action

immediately if actual performance is behind planned performance.

d.The project control process involves regularly gathering data on project performance,

comparing actual performance to planned performance, and taking corrective action

immediately if actual performance is behind planned performance.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

72.The project control process must occur regularly throughout the project and include all of the following except

a.Record information on changes to the project scope, schedule, and budget.

b.Gather data on actual performance.

c.Having a single inspection of the project’s deliverables at the end of the project.

d.Establish regular reporting meetings to compare actual to planned progress.

ANSWER: c

FEEDBACK: a. The project control process must occur regularly throughout the project and also:Establish

regular reporting meetings to compare actual to planned progress. Gather data on actual

performance.Record information on changes to the project scope, schedule, and budget.

b.The project control process must occur regularly throughout the project and also:Establish

regular reporting meetings to compare actual to planned progress. Gather data on actual

performance.Record information on changes to the project scope, schedule, and budget.

c.The project control process must occur regularly throughout the project and also:Establish

regular reporting meetings to compare actual to planned progress. Gather data on actual

performance.Record information on changes to the project scope, schedule, and budget.

d.The project control process must occur regularly throughout the project and also:Establish

regular reporting meetings to compare actual to planned progress. Gather data on actual

performance.Record information on changes to the project scope, schedule, and budget.

73.The key to effective project control is measuring actual progress and comparing it to planned progress on a timely

and regular basis and

a.taking any needed corrective action immediately.

b.leaving the project to self-correct.

c.fast tracking all the activities in the project until the project is ahead of schedule.

d.making sure the critical path doesn’t change.

ANSWER: a

FEEDBACK: a. The key to effective project control is measuring actual progress and comparing it to planned

progress on a timely and regular basis and taking any needed corrective action immediately.

b.The key to effective project control is measuring actual progress and comparing it to planned

progress on a timely and regular basis and taking any needed corrective action immediately.

c.The key to effective project control is measuring actual progress and comparing it to planned

progress on a timely and regular basis and taking any needed corrective action immediately.

d.The key to effective project control is measuring actual progress and comparing it to planned

progress on a timely and regular basis and taking any needed corrective action immediately.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

74.With respect to the project schedule, changes can result in any of the following except

a.the addition or deletion of activities.

b.the initial planning and sequencing of activities.

c.changes to estimated durations for specific activities.

d.a new required completion time for the project.

ANSWER: b

FEEDBACK: a. With respect to the project schedule, changes can result in the addition or deletion of activities,

resequencing of activities, changes to estimated durations for specific activities, or a new

required completion time for the project.

b.With respect to the project schedule, changes can result in the addition or deletion of activities,

resequencing of activities, changes to estimated durations for specific activities, or a new

required completion time for the project.

c.With respect to the project schedule, changes can result in the addition or deletion of activities,

resequencing of activities, changes to estimated durations for specific activities, or a new

required completion time for the project.

d.With respect to the project schedule, changes can result in the addition or deletion of activities,

resequencing of activities, changes to estimated durations for specific activities, or a new

required completion time for the project.

75.If the planned corrective actions do not result in an acceptable schedule, then

a.the project should be terminated.

b.the steps for schedule control need to be repeated.

c.the original project plan was best and should be used.

d.the customer should decide what should be done.

ANSWER: b

FEEDBACK: a. If the planned corrective actions do not result in an acceptable schedule, these steps need to be

repeated.

b.If the planned corrective actions do not result in an acceptable schedule, these steps need to be

repeated.

c.If the planned corrective actions do not result in an acceptable schedule, these steps need to be

repeated.

d.If the planned corrective actions do not result in an acceptable schedule, these steps need to be

repeated.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

76.A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities

that

a.are near term and those with long durations.

b.are short in duration and can be easily completed.

c.have the lowest cost.

d.are scheduled at the end of the project.

ANSWER: a

FEEDBACK: a. A concentrated effort to accelerate project progress must be applied to the paths with negative

slack to activities that are near term and those with long durations.

b.A concentrated effort to accelerate project progress must be applied to the paths with negative

slack to activities that are near term and those with long durations.

c.A concentrated effort to accelerate project progress must be applied to the paths with negative

slack to activities that are near term and those with long durations.

d.A concentrated effort to accelerate project progress must be applied to the paths with negative

slack to activities that are near term and those with long durations.

77.Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of

a.no change in costs and an increase in scope.

b.a decrease in costs and an expansion in scope.

c.an increase in costs or a reduction in scope.

d.an decrease in costs and no change in scope.

ANSWER: c

FEEDBACK: a. Eliminating negative slack by reducing durations of activities will involve a trade-off in the form

of an increase in costs or a reduction in scope.

b.Eliminating negative slack by reducing durations of activities will involve a trade-off in the form

of an increase in costs or a reduction in scope.

c.Eliminating negative slack by reducing durations of activities will involve a trade-off in the form

of an increase in costs or a reduction in scope.

d.Eliminating negative slack by reducing durations of activities will involve a trade-off in the form

of an increase in costs or a reduction in scope.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

78.Schedule control involves four steps. Place these steps in their proper order by stating the letter sequence of their

proper order.

A.Analyzing the schedule to determine which areas may need corrective action

B.Recalculating the schedule to evaluate the effects of the planned corrective actions

C.Revising the plan to incorporate the chosen corrective actions

D.Deciding what specific corrective actions should be taken

a.A,B,C,D

b.A,D,C,B

c.D,A,C,B

d.D,A,B,C

ANSWER: b

FEEDBACK: a. Schedule control involves four steps:

1.Analyzing the schedule to determine which areas may need corrective action

2.Deciding what specific corrective actions should be taken

3.Revising the plan to incorporate the chosen corrective actions

4.Recalculating the schedule to evaluate the effects of the planned corrective actions

b.Schedule control involves four steps:

1.Analyzing the schedule to determine which areas may need corrective action

2.Deciding what specific corrective actions should be taken

3.Revising the plan to incorporate the chosen corrective actions

4.Recalculating the schedule to evaluate the effects of the planned corrective actions

c.Schedule control involves four steps:

1.Analyzing the schedule to determine which areas may need corrective action

2.Deciding what specific corrective actions should be taken

3.Revising the plan to incorporate the chosen corrective actions

4.Recalculating the schedule to evaluate the effects of the planned corrective actions

d.Schedule control involves four steps:

1.Analyzing the schedule to determine which areas may need corrective action

2.Deciding what specific corrective actions should be taken

3.Revising the plan to incorporate the chosen corrective actions

4.Recalculating the schedule to evaluate the effects of the planned corrective actions

79.Schedule control involves four steps. List the four steps in order.

ANSWER: Schedule control involves four steps:

1.Analyzing the schedule to determine which areas may need corrective action

2.Deciding what specific corrective actions should be taken

3.Revising the plan to incorporate the chosen corrective actions

4.Recalculating the schedule to evaluate the effects of the planned corrective actions

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

80.Agile project management is an approach to product development time while risk through continuous

interaction between the customer and small self-organizing teams that produce increments of working product.

a.reduce, minimizing

b.increase, maximizing

c.reduce, maximizing

d.increase, minimizing

ANSWER: a

81.The project team member also referred to as the customer representative and responsible for defining the customer

requirements and product features and for ensuring that the development team delivers an end product with the

required features is the

a.Scrum master.

b.project manager.

c.product owner.

d.sprint timer.

ANSWER: c

82.The development team develops, delivers, and demonstrates a.the entire product

b.working product increments

c.final team presentations and meeting agendas

d.only those products not contracted yet

ANSWER: b

during a sprint.

83.As a part of the Scrum technique in agile project management, a sprint is usually one to four

a.days.

b.minutes.

c.weeks.

d.months.

ANSWER: c

84.The facilitator for the Scrum development process during a sprint whose primary job is to take actions to remove or

reduce any obstacles, barriers, or constraints that are impeding progress of the development team toward

accomplishing their work tasks and that may negatively impact the successful production and demonstration of a

deliverable working product increment by the end of the sprint time is the

a.Scrum master.

b.project manager.

c.product owner.

d.sprint timer.

ANSWER: a

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.Chapter 5: Developing the Schedule

85.The Scrum master is team.

a.the same, has indirect

b.the same, has direct

c.not the same, has direct

d.not the same, does not have direct

ANSWER: d

as a project manager in that he responsibility for the people on the development

86.Describe the agile project management for a project where a Scrum master is facilitating the Scrum development

process for a software development project. Include a description of the six steps in the agile project management

process.

ANSWER: Answers will include the six steps of the agile project management process.

The agile project management process includes: a) establishing the rationale, description, funding

amount, and target completion date for the final end product (deliverable) and authorizing the project,

b) defining the product requirements and creating an ordered product backlog of prioritized specific

requirements and product features, c) having a sprint planning meeting and creating the sprint backlog

list, d) having a daily scrum meeting, also known as the daily standup and usually limited to 15 minutes,

e) having a sprint review meeting at the end of the sprint, and f) having a sprint retrospective meeting

at the end of the sprint.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

There are no reviews yet.

Add a review

Be the first to review “Successful Project Management 6th Edition By Jack Gido Jim Clements – Test Bank”

Your email address will not be published. Required fields are marked *

Category:
Updating…
  • No products in the cart.